Geotechnical Engineering and Engineering Geology
  • Date submitted
    2021-04-19
  • Date accepted
    2022-05-25
  • Date published
    2022-07-13

Development of the technology of stowing the developed space during mining

Article preview

An analysis of the world experience in the development of potash deposits shows that the main problems arising during their development are a high level of mineral losses, an increased risk of flooding of mine workings as a result of water-proof layer discontinuance and the development of emergency water inflows in the mined-out spaces. Reduction of potash ore losses can be achieved by using a long-pillar mining system, but this method is limited by the peculiarities of the geological structure of the potash deposits and the need to preserve the continuity of the water-proof layer during its underworking. The safety of underworking of the water-proof layer can be improved by using the stowing of the developed longwall space. However, the question of the influence of the stowing on the height of the zone of water supply cracks development remains little-studied. The world experience of stowing the developed spaces in the development of layers with long pillars is analyzed and the technology of placing the stowing masses, which can solve these problems, is proposed. The considered technology and the proposed solutions are supported by laboratory tests of stowing materials and mathematical modeling of deformation zones in the overlying rocks.

How to cite: Kovalskii E.R., Gromtsev K.V. Development of the technology of stowing the developed space during mining // Journal of Mining Institute. 2022. Vol. 254 . p. 202-209. DOI: 10.31897/PMI.2022.36
Geotechnical Engineering and Engineering Geology
  • Date submitted
    2021-02-20
  • Date accepted
    2021-10-18
  • Date published
    2021-12-16

Thermal protection implementation of the contact overheadline based on bay controllers of electric transport traction substations in the mining industry

Article preview

The article presents the principle of thermal protection of the contact overheadlineand substantiates the possibility of practical implementation of this principle for rail electric transport in the mining industry. The algorithm for the implementation of modern digital protection of the contact overhead line as one of the functions of the controller is described. A mathematical model of thermal protection is proposed, which follows from the solution of the heat balance equation. The model takes into account the coefficient of the electrical networktopology, as well as the coefficient of consumption of the current-carrying core of the cable, which determines the reduction in the conducting section from contact erosion and the growth of oxide films. Corrections for air flows are introduced when receiving data from an external anemometer, via telemechanics protocol. The mathematical model was tested by writing a real thermal protection program in the C programming language for the bay controller, based on the circuitry of which is the STM32F407IGT6 microcontroller for the microcontroller unit. Verification tests were carried out on a serial bay controller in 2020. The graphs for comparing the calculated and actual values of temperatures, with different flow rates of the current-carrying conductor of the DC cable, are given. To obtain data, telemechanics protocols IEC 60870-104 and Modbus TCP, PLC Segnetics SMH4 were used.

How to cite: Lantsev D.Y., Frolov V.Y., Zverev S.G., Uhrlandt D., Valenta J. Thermal protection implementation of the contact overheadline based on bay controllers of electric transport traction substations in the mining industry // Journal of Mining Institute. 2021. Vol. 251 . p. 738-744. DOI: 10.31897/PMI.2021.5.13
Oil and gas
  • Date submitted
    2018-07-21
  • Date accepted
    2018-09-14
  • Date published
    2018-12-21

Natural ventilation of gas space in reservoir with internal floating roof

Article preview

The article deals with safe operation issues of vertical steel reservoirs with an internal floating roof when storing volatile oil products. The purpose of the work is to study the influence of ventilation openings area and wind speed on the duration of explosive state of vertical reservoirs with an internal floating roof. The influence of ventilation pipes' dimensions and the wind speed on the duration of explosive state of the reservoir has been studied. Method for calculating this time is proposed. It is shown that natural ventilation of the reservoir gas space is caused by the effect of two forces, which are formed due to: 1) the density difference between the vapor-air mixture in the reservoir and outside air; 2) wind pressure occurring on the roof of the reservoir. An algorithm for calculating the duration of reservoir being in an explosive state with wind pressure and no wind is obtained. The greater the difference in geodetic marks of the central and peripheral nozzles, the more efficient the ventilation. This distance will be greatest if the lower ventilation pipes are located on the upper belt of the reservoir or the reservoir is equipped with an air drain. Increase in wind speed of more than 10 m/s does not significantly affect the duration of the reservoir being in an explosive state. Increasing the diameter of the central nozzle from 200 to 500 mm can significantly reduce the duration of the reservoir degassing in windless weather.

How to cite: Karavaichenko M.G., Fathiev N.M. Natural ventilation of gas space in reservoir with internal floating roof // Journal of Mining Institute. 2018. Vol. 234 . p. 637-642. DOI: 10.31897/PMI.2018.6.637
Geoecology and occupational health and safety
  • Date submitted
    2017-12-27
  • Date accepted
    2018-03-22
  • Date published
    2018-06-22

Mathematical model of heat exchange processes for heat ptotective cooling suit of a rescuer

Article preview

Fires are followed by the range of factors hazardous for human health; a radiant thermal stream accompanied by the high temperature of the environment is one of these factors. For protection of firemen special protective clothing from heat impact and the insulation type clothing are used. The paper demonstrates that the concept of action of such clothing is based on the passive heat protection owing to the use of materials with low conducting capacity or high specific heat. The time of effective protection of a suit is not considerable which reduces the duration of work under the unfavorable climatic conditions drastically, increases the work labor input, leads to the hyperthermia. One of the ways focused on the improvement of the heat protective clothing is a design of suits with cooling, which is stated in the paper. The paper shows that the developed heat protective suits on the basis of water-ice cooling elements are not widely used due to considerable costs. A more reasonable idea refers to the design of heat protective suits with cooling by using running water as the most available coolant circulating along polyvinylchloride pipes arranged between the layers of a suit.

How to cite: Alabev V.R., Zavyalov G.V. Mathematical model of heat exchange processes for heat ptotective cooling suit of a rescuer // Journal of Mining Institute. 2018. Vol. 231 . p. 326-332. DOI: 10.25515/PMI.2018.3.326
Geoecology and occupational health and safety
  • Date submitted
    2015-10-18
  • Date accepted
    2015-12-01
  • Date published
    2016-08-22

Effect of surface geometry and insolation on temperature profile of green roof in Saint-Petersburg environment

Article preview

The paper addresses an issue of creating an environment favorable for the life in megacities by planting vegetation on the rooftops. It also provides information about rooftop greening practices adopted in other countries. The issues of ‘green roof’ building in climatic conditions of Saint Petersburg and roof vegetation impact on the urban ecosystem are examined. Vegetation composition quality- and quantity-wise has been proposed for the roof under research and a 3D model of this roof reflecting its geometric properties has been developed. A structure of roof covering and substrate qualitative composition is presented. An effect of rooftop geometry on the substrate temperature is explored. The annual substrate temperature and moisture content in different parts of the roof have been analyzed. Results of thermal imaging monitoring and insolation modelling for different parts of green roof surface are presented.

How to cite: Ignatev S.A., Kessel D.S. Effect of surface geometry and insolation on temperature profile of green roof in Saint-Petersburg environment // Journal of Mining Institute. 2016. Vol. 220 . p. 622-626. DOI: 10.18454/PMI.2016.4.622
Geotechnology for development of solid mining fields
  • Date submitted
    2013-07-20
  • Date accepted
    2013-09-04
  • Date published
    2014-03-17

Some approaches to secure mining of potash deposits

Article preview

The basic aspects of safe mining of potash deposits is reviewed. Practical examples of the mechanism and possible consequences of violating the integrity of the waterproof rock strata are described. Use of remote non-destructive monitoring system for non-destructive integrity breeds of the waterproof rock strata is proposed.

How to cite: Kovalev O.V., Mozer S.P. Some approaches to secure mining of potash deposits // Journal of Mining Institute. 2014. Vol. 207 . p. 55-59.
Qestion of the geoecology
  • Date submitted
    2013-07-22
  • Date accepted
    2013-09-24
  • Date published
    2014-03-17

Contemporary Problems of salvaging drill cuttings on the Western Siberia oilfields of the final stage of development

Article preview

The article deals with the problem of disposing of industrial and technological drilling wastes due to the application of salt biopolymer drilling fluids for extraction of residual oilfields of Western Siberia, which are at an final stage of development using the technology of directional drilling. The problem of disposal of drilling waste in the oilfields of the final stage of development is proposed to solve through the introduction of protective functions of the complex engineering activities, including, the development of waterproofing layer of clay cuttings, which is formed by drilling the top of the production casing, for different host rock cuttings.

How to cite: Katsilo V.V. Contemporary Problems of salvaging drill cuttings on the Western Siberia oilfields of the final stage of development // Journal of Mining Institute. 2014. Vol. 207 . p. 171-174.
Industrial safety and health care in mining
  • Date submitted
    2013-07-02
  • Date accepted
    2013-09-01
  • Date published
    2014-03-17

Analytical estimation of aerodynamic characteristics of the main roof collapse

Article preview

The article describes the formulas for calculation of air flow characteristics, that originates from the main roof collapse and also it has been made analysis of variates, that form their parts.

How to cite: Smirnyakov V.V. Analytical estimation of aerodynamic characteristics of the main roof collapse // Journal of Mining Institute. 2014. Vol. 207 . p. 151-154.
Industrial safety and health care in mining
  • Date submitted
    2013-07-16
  • Date accepted
    2013-09-20
  • Date published
    2014-03-17

Choice and valuation of similarity parameters for aero-gas-dynamic modeling with main roof collapse

Article preview

The article describes the necessary conditions for similarity parameters choosing for aero-gas-dynamic modeling with main roof collapse and it has been made analysis of them.

How to cite: Smirnyakov V.V. Choice and valuation of similarity parameters for aero-gas-dynamic modeling with main roof collapse // Journal of Mining Institute. 2014. Vol. 207 . p. 147-150.
Geomechanics, geodesy, mine surveying and cadastre
  • Date submitted
    2010-07-23
  • Date accepted
    2010-09-28
  • Date published
    2011-03-21

Sistaining mining in whole different rigidity

Article preview

Studies conducted in the mines «Rostovugol», showed that, for assessing the sustainability of preparatory excavations in the management of sewage treatment works is enough to determine the allowable values of convergence of the roof and ground-level workings and potential energy of elastic deformation of the pillars. These indicators can be used in the coal mines of other basins.

How to cite: Gorshkov L.K., Kokoev S.G. Sistaining mining in whole different rigidity // Journal of Mining Institute. 2011. Vol. 189 . p. 206-209.
Problems in geodynamic safety in the exploration of solid deposits
  • Date submitted
    2009-10-28
  • Date accepted
    2009-12-25
  • Date published
    2010-09-22

Prediction of dynamic manifestations of rock pressure in the all over automated longwalls

Article preview

The support control system «MARCO» has programs for the estimation of a geomechanical situation around the face by continuous measurements of pressure in the legs of support. The analysis of the face convergence allows to predict the possibility of a rock burst. The seam’s reaction on the shearer or plough influence may be the dangerous main roof collapse into the mine-out space of longwall.

How to cite: Roiter M., Kurfyurst V., Mairkhofer K., Veksler J. Prediction of dynamic manifestations of rock pressure in the all over automated longwalls // Journal of Mining Institute. 2010. Vol. 188 . p. 36-39.
Problems in geodynamic safety in the exploration of solid deposits
  • Date submitted
    2009-10-07
  • Date accepted
    2009-12-22
  • Date published
    2010-09-22

Providing of safe conditions for mining of shaftbottom protective pillars in deep ore mines at Тalnakh

Article preview

Consideration is given to the causes complicating the mining of shaftbottom pillar and protection of shaft lining. The analysis is given to the formation of stress-strain state of the protective pillar and its enclosing rocks. Practical recommendations are given for control of deformation and stresses in the shaftbottom mass during extraction of protective pillars in deep ore mines at Talnakh.

How to cite: Zvezdkin V.A., Anokhin A.G., Galaov R.B. Providing of safe conditions for mining of shaftbottom protective pillars in deep ore mines at Тalnakh // Journal of Mining Institute. 2010. Vol. 188 . p. 50-53.
Problems in geodynamic safety in the exploration of solid deposits
  • Date submitted
    2009-10-30
  • Date accepted
    2009-12-09
  • Date published
    2010-09-22

Investigation of regularities of rock inrush forming in productive faces of сoal mines

Article preview

The aspect of maintenance of roof stability of active stopes in mines of the Western Donbass is considered in the article. The conclusion is drawn on the probability of coal falls formation during mining operations in disturbed areas. Principal causes of coal fall formation are considered on the bais of natural surveying observations. Connections between technological parameters of longwall and geometrical parameters of disturbance are established.

How to cite: Khalimendik Y.M., Brui A.V., Chemakina M.V. Investigation of regularities of rock inrush forming in productive faces of сoal mines // Journal of Mining Institute. 2010. Vol. 188 . p. 70-73.
Geodesy, geomechanics and underground construction
  • Date submitted
    2009-08-22
  • Date accepted
    2009-10-19
  • Date published
    2010-02-01

The substantiation of reinforcing support of preparation mines in the ore massive of the Yakovlevskiy deposit

Article preview

The paper justifies a design of reinforcing mine support of the protective roof at the priority high-grade ore mining site of the Yakovlevskiy deposit. Experience of mine roadway support with the KMP-A3 standing support has been analyzed. A reinforcing support is offered consisting of rock bolts back bracing the ore exposure, which best fits with continuous miner roadheading and consolidating stowing (concrete).

How to cite: Antonov Y.N., Sinegubov V.Y. The substantiation of reinforcing support of preparation mines in the ore massive of the Yakovlevskiy deposit // Journal of Mining Institute. 2010. Vol. 186 . p. 94-98.
Problems in geomechanics of technologeneous rock mass
  • Date submitted
    2009-07-22
  • Date accepted
    2009-09-18
  • Date published
    2010-04-22

Higher grade filling due to horizontal layers extraction in Yakovlevsky ore deposit

Article preview

A complex of technology and organization methods to higher grade filling due to horizontal layers system of extraction rich ferrous metal ores for various stages of mining is presented.

How to cite: Zubov V.P., Antonov A.A., Lugovskoi Y.N., Morozov M.D., Mikhailenko O.V. Higher grade filling due to horizontal layers extraction in Yakovlevsky ore deposit // Journal of Mining Institute. 2010. Vol. 185 . p. 25-30.
Problems in geomechanics of technologeneous rock mass
  • Date submitted
    2009-07-29
  • Date accepted
    2009-09-15
  • Date published
    2010-04-22

Preconditions for application of supports of different types in productive workings of low-thick gently-pitching deposits in tectonically stressed massif (for conditions of the Karnasurt ore mine)

Article preview

The paper presents the data on the mining-geological conditions for mining and types of stope supports applied at the Karnasurt Mine, the Lovozersky rare-metal deposit. The peculiar feature of mining conditions is the presence of high subhorizontal tectonic stresses in the rock masses, which make the stope roofs more stable, allowing application of non-reinforced types of support.

How to cite: Lovchikov A.V., Matytsyn A.V. Preconditions for application of supports of different types in productive workings of low-thick gently-pitching deposits in tectonically stressed massif (for conditions of the Karnasurt ore mine) // Journal of Mining Institute. 2010. Vol. 185 . p. 68-70.
Problems in geomechanics of technologeneous rock mass
  • Date submitted
    2009-07-05
  • Date accepted
    2009-09-25
  • Date published
    2010-04-22

Active methods for control of geomechanical state of rock mass in coal deposit mining under complicated geological-and-mining conditions

Article preview

The paper presents the main technologies, characteristics, schematic diagrams and parameters of active methods for control of geomechanical state of technogenic rock mass, domain and technical-and-economical efficiency of their industrial application.

How to cite: Voskoboev F.N., Semenov Y.A., Zvezdkin V.A. Active methods for control of geomechanical state of rock mass in coal deposit mining under complicated geological-and-mining conditions // Journal of Mining Institute. 2010. Vol. 185 . p. 99-101.
Problems in geomechanics of technologeneous rock mass
  • Date submitted
    2009-07-04
  • Date accepted
    2009-09-10
  • Date published
    2010-04-22

Provision of safe coal mining with due account оf cleanup works at adjacent seams

Article preview

During planning of mining works with coal series it is important to take into consideration mining conditions of each mine layer, to determine presence of natural and technogenic abnormal areas at its place and to appreciate their potential level of influence on the increase of rock pressure manifestations in the development and productive workings. In comparable conditions the most negative manifestations of rock pressure can be observed in roadways of neighboring low layer, when they are disposed in range of mutual action of abnormal areas of natural and technogenic origins.

How to cite: Ilyashov M.A. Provision of safe coal mining with due account оf cleanup works at adjacent seams // Journal of Mining Institute. 2010. Vol. 185 . p. 148-151.