Condition of the soil mass at the Moscow Canal hydroelectric complex No. 4 after seventy years of operation

Authors:
E. Yu. Nesynova1
A. I. Yudkevich2
About authors
  • 1 — Hydroproject
  • 2 — Hydroproject
Date submitted:
2002-06-10
Date accepted:
2002-07-14
Date published:
2003-03-20

Abstract

The state of the ground massif is evaluated according to three parameters: surface deformations, groundwater level position and filtration strength of the pounds. A conclusion is made about the unsatisfactory condition of the pound foundation of hydraulic unit No. 4, which requires measures for its stabilization.

Область исследования:
(Archived) Development regularities of technogenic and geological processes and phenomena
Funding:

None

Go to volume 153

Similar articles

Scientific legacy of V.D. Lomtadze and prospects for the development of engineering geology at the St. Petersburg Mining Institute
2003 R. E. Dashko, I. P. Ivanov
The cartographic model of engineering-geological environment of Professor V.D. Lomtadze and practical aspects of its implementation in Lithuania
2003 R. B. Mikshis, V. Ignatavichyus, V. Martsinkyavichyus
Development of V.D. Lomtadze's doctrine on the formation of physical and mechanical properties of clayey rocks during lithification
2003 E. I. Tkachuk
The use of isotope methods in the study of groundwater balance (Almeria, Spain)
2003 I. L. Kharkhordin, I. V. Tokarev
Study of paragenetic complexes of geological processes
2003 G. N. Dublyanskaya, V. N. Dublyanskii
Main factors determining the radon flux into the atmosphere in the conditions of Moscow
2003 P. S. Miklyaev, R. S. Ziangirov, T. B. Petrova