Development regularities of technogenic and geological processes and phenomena
  • Date submitted
    2002-06-10
  • Date accepted
    2002-07-14
  • Date published
    2003-01-01

Condition of the soil mass at the Moscow Canal hydroelectric complex No. 4 after seventy years of operation

Article preview

The state of the ground massif is evaluated according to three parameters: surface deformations, groundwater level position and filtration strength of the pounds. A conclusion is made about the unsatisfactory condition of the pound foundation of hydraulic unit No. 4, which requires measures for its stabilization.

How to cite: Nesynova E.Y., Yudkevich A.I. Condition of the soil mass at the Moscow Canal hydroelectric complex No. 4 after seventy years of operation // Journal of Mining Institute. 2003. Vol. 153. p. 91-92.