Determination of open pit boundaries by the method of using the acceptable average stripping ratio

Authors:
O. V. Shpansky
A. A. Kovpak
Date submitted:
1971-07-29
Date accepted:
1971-09-21
Date published:
1972-07-07

Abstract

Determination of open pit boundaries is one of the main tasks of designing the field development. Its solution is usually carried out in three stages. The boundary stripping ratio is calculated, then the method of delineation is selected, and, finally, according to the selected method, the quarry is delineated.

Область исследования:
(Archived) Without section
Funding:

None

Go to volume 63

Similar articles

Analytical determination of the direction of deepening of a circular pit
1972 L. A. Slutsman
Estimation of the uniformity of mining transportation equipment operation in the quarries of the Polar Region
1972 A. V. Zhukov
Criteria for assessing the optimality of the direction of mining operations in a quarry
1972 A. I. Arsentiev
Classification of stripping methods and systems of development of quarry fields
1972 A. I. Arsentiev
Statistical analysis of working area width
1972 A. F. Bogachev, D. I. Shitov
Influence of granite fracturing on the indicators of thermal drilling of wells
1972 V. K. Bubok, I. Yu. Bukin