Submit an Article
Become a reviewer
Vol 195
Pages:
138-141
Download volume:
RUS
Article

Determining the mine working height for the development of tailing dumps hydraulic excavator backdigger

Authors:
G. A. Kholodnyakov1
K. R. Argimbaev2
S. P. Reshetnyak3
About authors
  • 1 — Ph.D., Dr.Sci. professor Saint Petersburg State Mining University
  • 2 — post-graduate student Saint Petersburg State Mining University
  • 3 — Ph.D., Dr.Sci. associate professor, leading technician «Giproshaht»
Date submitted:
2011-07-01
Date accepted:
2011-09-26
Date published:
2012-04-05

Abstract

Development water sated tailing dump are accompanied explosive failure banks even at their height less 10 meters. Thereupon, the problem decision on research competence a slope and to a choice of optimum height production a dredge face «backdigger», established on the top platform tailing dump, will allow to reduce equipment downtimes and to increase intensity mining.

Область исследования:
(Archived) Topical issues in mining of ore and nonmetallic minerals
Keywords:
tailing dump excavator «backdigger» tailing height of face algorithm program intensity
Funding:

None

Go to volume 195

References

  1. Nurok G.A., Lugovskaya A.G., Sherstukov A.D. Hydraulic-mine dumps at strip-pits. Moscow, 1973.
  2. Fisenko I.V. Stability of open pit slopes. Moscow, 1973.
  3. Kholodnyakov G.A., Argimbaev K.R., Ikonnikov D.A. Determining physical and mechanical properties of tailings of iron-bearing tailing dumps // Mining informational and Analytical Bulletin. Moscow, 2011.
  4. Kholodnyakov G.A., Argimbaev K.R., Ikonnikov D.A. Excavating and loading equipment for the development of semi-dry tailing dumps // Development of mineral resources of the North. Problems and solutions. Vorkuta, 2011. Vol. 1.

Similar articles

Design of tunnel lining of main line tunnels based on the evaluation of stress distribution patterns in tunnel lining
2012 A. G. Protosenya, V. L. Trushko, M. A. Karasev, D. V. Sidorov
The designing of the constructions of the pillar underground station with applying of the low-settle building technology
2012 A. G. Protosenya, P. A. Demenkov, M. A. Karasev, N. A. Belyakov, K. P. Bezrodnyi, V. A. Maslak
Prospective ways of diamondiferous rock enrichment wastes utilization at M.V.Lomonosov diamond deposit
2012 A. Yu. Oblitsov, V. A. Rogalev
Analysis of the effectiveness of regulations in the subsoil usage (illustrated on regulating the level of cost oil under psas)
2012 N. E. Chebaeva
Amount of explosive destruction zones for cracked rocks with different crack filler for example Mikhailovsky GOK
2012 M. G. Menzhulin, A. V. Fedoseev
Control of gasevolutioncoal-beds – the key factor of creation of safe working conditions
2012 I. V. Kurta