Design of tunnel lining of main line tunnels based on the evaluation of stress distribution patterns in tunnel lining

Authors:
A. G. Protosenya1
V. L. Trushko2
M. A. Karasev3
D. V. Sidorov4
About authors
  • 1 — Saint Petersburg State Mining University
  • 2 — Saint Petersburg State Mining University
  • 3 — Saint Petersburg State Mining University
  • 4 — Saint Petersburg State Mining University
Date submitted:
2011-07-26
Date accepted:
2011-09-12
Date published:
2012-04-05

Abstract

Comparison of results of calculations of the tangential stresses on the inner contour of tunnel lining and radial stresses on the outer contour is done. Stresses are found by solving the problem of interaction in geomechanical system «lining-ground massif» in 2D and 3D model (single layer tunnel lining and double layer tunnel lining). Area of correct application of 2D models are revealed.

Go to volume 195

References

  1. Булычев Н.С. Расчет крепи капитальных горных выработок / Н.С.Булычев, Б.З.Амусин, А.Г.Оловянный. М.: Недра, 1974. 320 с.
  2. Карасев М.А. Натурные обследования тоннелей Санкт-Петербургского метрополитена и результаты численного моделирования напряженно-деформированного состояния тюбинговой обделки // Инновации в геонауке и геоинженерии / Фрайбергская горная академия, Фрайберг. 2008. С.272-280.
  3. Протосеня А.Г. Пространственное напряженно- деформированное состояние и оценка прочности тюбинговой обделки тоннелей // Метро и тоннели (Тоннельная ассоциация России). 2008. № 4. С. 23-26.
  4. Протосеня А.Г. Расчет напряженно-деформированного состояния тюбинговых крепей и обделок на основе пространственных моделей / А.Г.Протосеня, М.А.Карасев // Освоение минеральных ресурсов Севера: проблемы и решения: Тр. 5-й Межрегион. практ. конф. Воркута, 2007. С. 45-49.

Similar articles

Estimation of atmospheric air pollution аt construction and operation of traffic tunnel
2012 S. G. Gendler, V. A. Rogalev
Possible solution for extraction of gas-bearing coal seams by highly productive mining complexes
2012 A. V. Leisle
Conception of mining and chemical company competitivness growth strategy creation
2012 A. A. Ilinova
Hydro-geological monitoring on the Jakovlevsky mine as implement of increase safety conducting mine second working in difficult mine-geological conditions
2012 R. E. Dashko, E. N. Kovaleva
Self-propellet rail transporting mechanisms with even driving wheels
2012 N. A. Belous, A. V. Bolshunov, G. V. Sokolova
The distribution of late quaternary glacial-marine deposite on the norternmost part оf Novaya Zemlya shelf
2012 D. E. Dorechkina, P. V. Rekant, D. A. Korshunov, A. D. Portnov