The designing of the constructions of the pillar underground station with applying of the low-settle building technology
Authors:
About authors
- 1 — Ph.D., Dr.Sci. professor Saint Petersburg State Mining University
- 2 — Ph.D. associate professor Saint Petersburg State Mining University
- 3 — Ph.D. associate professor Saint Petersburg State Mining University
- 4 — post-graduate student Saint Petersburg State Mining University
- 5 — Ph.D., Dr.Sci. deputy director in the field of scientific researches JSC «Lenmetrogiprotrans»
- 6 — director general JSC «Lenmetrogiprotrans»
Abstract
The intelligent technology of designing of the constructions of pillar underground station is adduced. Station is building with applying of low-settle technology, which takes into consideration main stages of the building process. The scheme of interaction of the system «support lining-soil massif» was accepted as basic scheme of calculations. The calculations of the stress-strain condition of constructions was performed with applying of finite-elements method.
Область исследования:
(Archived) Topical issues in mining of ore and nonmetallic minerals
Keywords:
underground station
permanent support lining
soil massif
temporary support lining
model
stress
References
- Protosenya A.G., Belyakov N.А. The determination of the volume stress-strain conditions of the soil massif in the face area of the tunnel in conditions of drafting with using of contledge of the face // Notes of Mining Institute. 2011. Vol.190. P.149-163.
- Demenkov P.A. The influence of building technology on forming of the load in conditions of the underground column-type station «Komendantsky prospect» of SaintPetersburg underground // The Proceedings of Mining Institute. Saint Petersburg, 2004. Vol.155. P.102-105.
Similar articles
Automatic adjustment of metrology performance meter random signal transducer analyzer liquid flows
2012 R. M. Proskuryakov, A. V. Kopteva, I. N. Voityuk
Design features of replacement work equipment of peat excavation laoding machine
2012 D. O. Nagornov, E. A. Kremcheev
Approach to perfection and progress of the industrial infrastructure (on the example of the deposit «Glubokoe» on extraction of plaster in the Arkhangelsk area)
2012 V. A. Modyanova
Determining the mine working height for the development of tailing dumps hydraulic excavator backdigger
2012 G. A. Kholodnyakov, K. R. Argimbaev, S. P. Reshetnyak