Determining the mine working height for the development of tailing dumps hydraulic excavator backdigger
About authors
- 1 — Ph.D., Dr.Sci. professor Saint Petersburg State Mining University
- 2 — post-graduate student Saint Petersburg State Mining University
- 3 — Ph.D., Dr.Sci. associate professor, leading technician «Giproshaht»
Abstract
Development water sated tailing dump are accompanied explosive failure banks even at their height less 10 meters. Thereupon, the problem decision on research competence a slope and to a choice of optimum height production a dredge face «backdigger», established on the top platform tailing dump, will allow to reduce equipment downtimes and to increase intensity mining.
Область исследования:
(Archived) Topical issues in mining of ore and nonmetallic minerals
Funding:
None
References
- Nurok G.A., Lugovskaya A.G., Sherstukov A.D. Hydraulic-mine dumps at strip-pits. Moscow, 1973.
- Fisenko I.V. Stability of open pit slopes. Moscow, 1973.
- Kholodnyakov G.A., Argimbaev K.R., Ikonnikov D.A. Determining physical and mechanical properties of tailings of iron-bearing tailing dumps // Mining informational and Analytical Bulletin. Moscow, 2011.
- Kholodnyakov G.A., Argimbaev K.R., Ikonnikov D.A. Excavating and loading equipment for the development of semi-dry tailing dumps // Development of mineral resources of the North. Problems and solutions. Vorkuta, 2011. Vol. 1.
Similar articles
Study of engineering-geological and microbiological factors for assessing the dynamics of fracture in tunnel highway Saint Petersburg – Kiev
2012 R. E. Dashko, K. V. Pankratova, A. A. Korobko
Automatic adjustment of metrology performance meter random signal transducer analyzer liquid flows
2012 R. M. Proskuryakov, A. V. Kopteva, I. N. Voityuk
Selecting parameters of wind and diesel power plant for power supply of mining intallations
2012 B. N. Abramovich, A. A. Belskii
Probabilistic approach to the assessment of energy transmissions of mining machines
2012 I. E. Zvonarev, A. S. Fokin, S. L. Ivanov