Submit an Article
Become a reviewer
Vol 198
Pages:
131-133
Download volume:
RUS
Article

To the question of maintenance of permanent workings ventilation-waste floor in techtonic stressed zones «Big Gorst» of «Taimyr» mine

Authors:
V. A. Zvezdkin1
V. N. Karelin2
T. S. Mushtekenov3
About authors
  • 1 — Ph.D. leading research assistant National Mineral Resources University (Mining University)
  • 2 — deputy director of the mineral complex ZF OJSC MMK «Norilsk Nickel»
  • 3 — chief engineer of «Taimyr» mine ZF OJSC MMK «Norilsk Nickel»
Date submitted:
2011-10-12
Date accepted:
2011-12-10
Date published:
2012-11-19

Abstract

Factors complicating drifting processes and barring in situ, disintegrated by tectonic burst- ing are considered. The analysis of stress-strain state formation of rock massif in the vicinity of tectonic disturbance is presented and practical recommendations concerning drifting and barring are given.

Область исследования:
(Archived) Innovation in designing of mining plants
Keywords:
mine capital developments fastening pressure deformation recommendation
Go to volume 198

References

  1. Advice on safe mining at Talnakhskiy and Oktyabrsky deposits prone and dangerous to rock bursts. Norilsk, 2001. 107 p.

Similar articles

Microstructual mechanical behaviour of soils
2012 M. A. Karasev
Optimization of protective pillars parameters of mine shafts at the ore mines of OJSC «MMK «Norilsk Nickel»
2012 Yu. I. Zuev, S. N. Zelentsov, E. I. Kuznetsova, V. A. Zvezdkin, V. N. Karelin
Optimization of drainage systems of developed and perspective polymetallic deposits of Leninogorsky area of Rudniy Altai
2012 V. B. Kolpakov
Mechanism of infuence on the powered roof support of rocks under different schemes of its failure above the mined-out space
2012 S. G. Baranov, M. A. Rozenbaum
Calendar planning in present-day geological and mining systems
2012 R. A. Bagateev
Experience in application of geophysical methods for stress-strain state of rock mass control with the goal of altering design solutions in liquidation the flooding of the emergency section of mine № 1-5 of the Barentsburg coal deposit
2012 M. V. Shvankin, S. N. Mulev, A. P. Skakun, E. N. Rabota