Condition of the soil mass at the Moscow Canal hydroelectric complex No. 4 after seventy years of operation
About authors
- 1 — Hydroproject
- 2 — Hydroproject
Abstract
The state of the ground massif is evaluated according to three parameters: surface deformations, groundwater level position and filtration strength of the pounds. A conclusion is made about the unsatisfactory condition of the pound foundation of hydraulic unit No. 4, which requires measures for its stabilization.
Область исследования:
(Archived) Development regularities of technogenic and geological processes and phenomena