Investigation of the efficiency of the cutting slot to reduce seismic impact during tunnel construction
Authors:
About authors
- Research assistant G.V. Plekhanov Saint Petersburg Mining Institute
Abstract
The paper considers the issue of seismic protection of the environment and protected objects during drilling and blasting method of tunneling. It is shown that the creation of a cut-off slot reduces the amplitude values of seismic blast waves at least three times. This experimental fact made it possible to use the cut-off slit for tunneling the gallery of the Krasno-Polyansky tunnel using blasting.
Область исследования:
(Archived) Mining. Ecology
Similar articles
Experimental-industrial tests of lime hydrochemical treatment of nepheline sludge from alumina production
2006 A. V. Starshinov
Role of physical culture in maintenance and restoration of working capacity of mining engineers
2006 G. V. Rudenko, S. V. Bakhvalova
Development of flushing technology when drilling horizontal wells by horizontal directional drilling units
2006 S. K. Pavlova
Increase of reliability of systems of accounting and control of energy consumption at mining enterprises
2006 E. V. Tatarenkov