Stripping and preparation of new horizons at formation of a working zone of a quarry

Authors:
I. A. Ishkulova
About authors
  • Postgraduate student G.V. Plekhanov Saint Petersburg Mining Institute
Date submitted:
2005-06-10
Date accepted:
2005-07-27
Date published:
2006-03-30

Abstract

When forming the lower part of the working zone of the open pit - opening and preparation of new horizons - insufficient attention is paid to the shape of the excavated space of the lower horizon, which often cannot provide the most rational parameters of the blasted block, and therefore the maximum length of the mining front, which should compensate for the deficit arising from the mining front on the upper horizons. The present work provides the formation of the shape and parameters of the preparatory excavation, its position relative to the ore deposit and ensuring the maximum length of the mining front, taking into account the rational use of drilling and blasting.

Область исследования:
(Archived) Mining. Ecology
Go to volume 167

Similar articles

Laws of distribution of concentration of solid particles during the flow of concentrated hydro-mixtures through pipelines
2006 I. A. Bostan, N. A. Ekimov
Justification of application of new composite materials in plugging solutions for cementing the borehole borehole space in the interval of perforation works
2006 R. A. Usmanov
Symbolism of the cross in archaic and Christian cultures
2006 R. V. Korchenkov, I. V. Trofimova
Methodology and practice of option accounting at justification of investment project Kovykta-China-South Korea
2006 D. A. Ilinskii
Research of strength and deformation properties of hydro-hematite ores of Yakovlevskoe deposit
2006 D. N. Petrov, D. B. Zykov
Justification of resource-saving technological schemes of mining of powerful steep formations
2006 E. V. Glushchenkov