Abstract

Research of cutoff grade influence on economic performances of mine as well as parameters and configuration of ore deposits with the help of the advanced geoinformation system were carried out. Computer modeling of an ore chute was made; the results of calculation were presented, involvement is given.

Область исследования:
Mining
Keywords:
cutoff grade condition ore deposit computer modeling
Funding:

None

Go to volume 186

References

  1. Boguslavskii Eh.I. Quality management ore / Saint Petersburg Mining Institute. Saint Petersburg, 2002. 78 р.
  2. Kaputin Yu.E. Information technology & economic appraisal of mining industry. Saint Petersburg: Nedra, 2008. 334 р.
  3. Dr. R.Pakalnis & Dr. R.Poulin. Quantifying Dilution for Underground Mine Operations / University of British Columbia. Vancouver, B.C. 1995. 420 р.

Similar articles

The substantiation of reinforcing support of preparation mines in the ore massive of the Yakovlevskiy deposit
2010 Yu. N. Antonov, V. Yu. Sinegubov
Advance of the metallurgical limestone shaft kilning process control system
2010 N. I. Koteleva
Definition of dependent cadastral value estimation indicators of urban land sections (on the example of Kostomuksha)
2010 O. Yu. Lepikhina
Experimental determination of vibration jaw crusher perfomance and characteristic of the crusher two-motor drive in no-load and nominal mode of operation
2010 S. Yu. Tyagushev, O. B. Shonin
New constructions of belt-ropes conveyors for the mountain enterprises
2010 Yu. D. Tarasov, A. V. Kopteva
Calculation of material streams of the pirometallurgical cycle of processing of copper sulphidic raw materials
2010 N. V. Danilova