Geomechanical substantiation of parameters of the fastening of railway tunnels in the conditions of the North Caucasus

Authors:
N. A. Belyakov
About authors
  • Student Saint Petersburg State Mining Institute (Technical University)
Date submitted:
2009-08-25
Date accepted:
2009-10-24
Date published:
2010-02-01

Abstract

The article presents the rationale of temporary supports used in the drilling of new mines, which provides for the construction of model projects of reconstruction of old tunnels. Finite-element method analyzed the changes of stress-strain state containing tunnel complex array during the drilling of new mines. Based on the analysis, a number of findings to explore the possibility of reducing the thickness of the permanent support of new mines in tunnel complex - the new tunnel, and transport and drainage culvert.

Область исследования:
(Archived) Geodesy, geomechanics and underground construction
Keywords:
tunnel temporary support permanent support stresses deformation reconstruction modeling
Go to volume 186

References

  1. Bulichev N.S. Mechanics of the underground constructions: The textbook for higher schools. The second edition. Moscov: Nedra, 1994. 382 р.

Similar articles

The unit for gravity concentration of fine particles
2010 Ya. V. Kuskova
The substantiation of reinforcing support of preparation mines in the ore massive of the Yakovlevskiy deposit
2010 Yu. N. Antonov, V. Yu. Sinegubov
Impact of the global financial crisis on German economy
2010 A. P. Rusakova, Yu. M. Sishchuk
Scheelites of Gavrilovskoe deposit (first find)
2010 A. E. Melnik
Complex geological engineering and geoenvironmental monitoring as a basis for creation of strategy of Saint Petersburg architectural and historical monuments conservation
2010 A. V. Shidlovskaya
Estimation of stresses in system «massive – support – shaft drift» at dynamic loadings
2010 I. E. Dolgiy, D. A. Kotikov