Selecting parameters of wind and diesel power plant for power supply of mining intallations

Authors:
B. N. Abramovich1
A. A. Belskii2
About authors
  • 1 — Ph.D., Dr.Sci. professor Saint Petersburg State Mining University
  • 2 — student Saint Petersburg State Mining University
Date submitted:
2011-07-13
Date accepted:
2011-09-04
Date published:
2012-04-05

Abstract

The paper is dedicated to analyzing the use of wind and diesel power plants for the power supply of mining facilities located remotely from centralized power supply networks. Regions which are promising in terms of using their wind potential are determined. An example of the network for using a wind and diesel power plant to supply submersible motors of centrifugal pumps in an oil well cluster is presented.

Область исследования:
(Archived) Mining electromechanics and mining equipment
Keywords:
average annual wind speed wind and diesel power plant submersible motor
Funding:

None

Go to volume 195

References

  1. Abramovich B.N., Belsky A.A., Yakovleva A.M. Renewable sources of energy for power supply of geograhically distributed mining industry facilities // The 37h week of science in Saint Petersburg State Polytechical University: Materials of international scientific practical conference. 2009. Vol.2.
  2. Starkov A.N., Landbreg L., Bezrukikh P.P., Borisenko M.M. Atlas of winds of Russia. Moscow, 2000.
  3. Nikolaev V.G. Methods and techniques of estimating and describing wind potential of Russia // Wind Industry in Russia: The report of the national conference (Moscow, Russia, 13 Nov. 2009). Saint Petersburg, 2010.

Similar articles

Mining complexes dismantling technologies at extraction of flat-lying thick coal seams with unstable rocks of the roof
2012 G. N. Karpov
Study of the ways saving to energy at transport of the oils
2012 S. V. Samolenkov, O. V. Kabanov
Estimation of atmospheric air pollution аt construction and operation of traffic tunnel
2012 S. G. Gendler, V. A. Rogalev
Ore reclaiming process flowsheets for the cyclical and continuous method of open-cast mining
2012 G. A. Kholodnyakov, A. O. Ipatova, D. A. Ikonnikov, K. R. Argimbaev
Long face ventilation performance improving in development of seam by pillarless technology
2012 V. S. Elkin
Determining the mine working height for the development of tailing dumps hydraulic excavator backdigger
2012 G. A. Kholodnyakov, K. R. Argimbaev, S. P. Reshetnyak