Submit an Article
Become a reviewer
Vol 249
Pages:
342-350
Download volume:

Improving the efficiency of the technology and organization of the longwall face move during the intensive flat-lying coal seams mining at the Kuzbass mines

Authors:
Аndrey A. Meshkov1
Oleg I. Kazanin2
Andrey A. Sidorenko3
About authors
Date submitted:
2021-01-18
Date accepted:
2021-05-21
Date published:
2021-09-20

Abstract

The reasons for the lag of the indicators of the leading Russian coal mines engaged in the longwall mining of the flat-lying coal seams from similar foreign mines are considered. The analysis of the efficiency of the longwall face move operations at the JSC SUEK-Kuzbass mines was carried out. A significant excess of the planned deadlines for the longwall face move during the thick flat-lying seams mining, the reasons for the low efficiency of disassembling operations and the main directions for improving the technology of disassembling operations are revealed. The directions of ensuring the operational condition of the recovery room formed by the longwall face are considered. The recommended scheme of converged coal seams mining and a three-dimensional model of a rock mass to justify its parameters are presented. Numerical studies using the finite element method are performed. The results of modeling the stress-strain state of a rock mass in the vicinity of a recovery room formed under conditions of increased stresses from the boundary part of a previously mined overlying seam are shown. The main factors determining the possibility of ensuring the operational condition of the recovery rooms are established. It is shown that it is necessary to take into account the influence of the increased stresses zone when choosing timbering standards and organizing disassembling operations at a interbed thickness of 60 m or less. A sufficient distance from the gob of above- or undermined seams was determined to ensure the operational condition of the recovery room of 50 m, for the set-up room – 30 m. Recommendations are given for improving technology and organization of the longwall face move operations at the mines applied longwall mining of flat-lying coal seams with the formation of a recovery room by the longwall face.

Keywords:
underground mining coal seam multi-seam mining longwall equipment downtime recovery room stress-strain state
10.31897/PMI.2021.3.3
Go to volume 249

Introduction

The Kuznetsk coal basin is the main coal-producing region of Russia. It accounts for 251 million tons out of 445 million produced in Russia in 2019 (more than 56 % of all coal production). The main technology of underground coal mining in Russia – the longwall mining [1, 4, 29] – is characterized by a high level of mechanization and safety of mining operations [28, 30, 31]. The use of modern state-of-the art equipment in the longwall faces ensures the mining operations with record daily and monthly productivity, exceeding the productivity of the best longwalls in the leading coal-producing countries [5, 6, 28]. Thus, in 2017-2018, production from one longwall at the mine “Named after V.D.Yalevskiy” reached 1.4-1.6 million tons per month. However, the average annual longwall productivity of even the best Russian mines still significantly lag behind the longwall productivity of foreign coal mines [10, 11, 22], which, in our opinion, is explained by the long downtime of state-of-the art longwall equipment. The economic losses caused by equipment downtime can range from 5 to 40 million rubles per day, and the duration of downtime can reach 150-200 days a year. One of the main reasons for long downtime of state-of-the art longwall equipment is the lack of efficiency of longwall face move operations at the coal mines of Russia [2, 27].

The purpose of this work is to develop and justify technological and organizational solutions that create conditions for improving the efficiency of longwall face move during intensive flat-lying coal seams mining at Russian mines by identifying the causes of violations of the technological stability and the subsequent targeted impact on these causes through a comprehensive justification of the parameters of technological schemes and the organization of work.

Formulation of the problem

JSC SUEK-Kuzbass carries out underground coal mining in seven mines with simultaneous operation of up to nine longwalls. Most of the company's mines operate one longwall, only the mines “Named after S.M.Kirov” and “Named after V.D.Yalevskiy” operates by two longwalls. The frequency of longwall face move at coal mines is determined by the productivity of longwall and the volume of reserves within the longwall panel. The average frequency of the longwall face moves at the mines of JSC SUEK-Kuzbass is approximately one move per year. This frequency persists for many years, since the increase in the productivity of longwalls is accompanied by an increase in the size of the longwall panels. The planned period of longwall face move differs for medium-thickness and high-thickness seams due to a significant difference in the weight of the longwall face equipment. The weight of one shield for various types of shield supports used in mines for medium-thickness seams mining is less than 20 tons (for example, the Joy RS-2400/2*650 support shield weighs 16.9 tons), and for thick seams – 27-40 tons. At the mines of JSC SUEK-Kuzbass, the most advanced method of longwall face move is used, which provides the recovery room formation by the longwall face – the use of roof bolts and polymer mesh for reliable support of the recovery room. When medium-thickness seams mining, the planned duration of the longwall face move is 45-68 days, of which 15-18 days are spent on the recovery room formation. When mining thick seams, the planned duration is 61 days, of which 15-20 days is the recovery room formation.

To assess the effectiveness of the longwall face move operations at the mines of JSC SUEK-Kuzbass, the analysis was performed of 46 cases of longwall face moves (2014-2019) – 24 cases during the mining of medium-thickness seams (Table 1) and 22 cases during the mining of thick seams (Table 2).

Table 1

Results of the analysis of the efficiency of longwall face move operations during the medium-thickness seams mining

Mine

Year

Longwall number-disassembling / assembling

Longwall length, m

Distance of equipment transportation, m

Depth of mining, m

Extractable seam thickness, m

Exceeding the planned deadlines for the recovery room formation, day

Total excess of planned deadlines of longwall face move, day

Named after S.M.Kirov

2014

24-56/24-57

230/300

1300

290

2.3

20

10

Komsomolets

2014

17-32/17-33

300/300

1500

390

2.1

14

11

Named after S.M.Kirov

2015

24-56/ 24-57

300/300

2300

380

2.3

–2

15

Named after S.M.Kirov

2015

25-94/25-95

270/300

500

350

2.3

18

74

Komsomolets

2015

17-33/17-34

300/300

1500

380

2.1

8

21

Named after A.D.Ruban

2016

12-12/12-10

220/220

2250

240

2.3

11

19

Named after S.M.Kirov

2016

24-57/24-58

300/303

2400

410

2.3

–1

18

Komsomolets

2016

17-34/17-31

300/200

1500

265

2.1

1

16

Polysaevskaya

2016

17-47/17-49

300/300

300

330

1.6

9

42

Named after A.D.Ruban

2017

12-10/12-08

220/220

2500

200

2

6

–10

Named after S.M.Kirov

2017

24-58/24-59

300/304

2600

430

2.3

–3

–14

Komsomolets

2017

17-31/17-31 bis

300/300

1400

400

2.1

–1

–10

Komsomolets

2017

17-31 bis/17-35

300/220

1450

400

2.1

–1

6

Polysaevskaya

2017

17-49/17-51

300/300

3000

310

1.6

2

20

Named after A.D.Ruban

2018

12-08/12-06

220/220

2650

140

2.1

5

14

Named after S.M.Kirov

2018

24-59/24-60

300/305

2900

430

2.3

–3

4

Named after S.M.Kirov

2018

25-96/25-101

300/300

1400

310

2.3

–3

26

Komsomolets

2018

17-35/18-46

300/300

5500

370

2.1

0

63

Named after A.D.Ruban

2019

12-06/12-04

220/220

2150

110

2.1

–1

44

Named after S.M.Kirov

2019

25-101/25-97-1

300/300

900

360

2.3

0

48

Named after S.M.Kirov

2019

25-97-1/25-97

300/300

3300

360

2.3

–1

90

Named after S.M.Kirov

2019

24-60/24-62

300/300

2900

470

2.3

2

107

Komsomolets

2019

18-46/18-47

300/300

2600

430

2.1

–2

16

Polysaevskaya

2019

17-51/17-53

300/300

3000

370

1.6

2

31

When mining medium-thickness seams, the average excess of the planned deadlines of longwall face move is 27 days, including the excess of the terms of the recovery room formation – 3 days. When mining thick seams, the average excess of the planned deadlines for longwall face move is 50 days, including 8 days during the recovery room formation (Table 2).  The longest duration of disassembling operations is observed at the mine “Named after V.D.Yalevskiy” (former mines N 7 and “Kotinskaya”), which is characterized by the highest longwalls productivity. It is the significant lag in the rate of the entries development for the new longwall panel from the rate of the longwall face advancing [2, 27] in the current situation that is the reason for the untimely preparation of new longwall panel and the main reason for the increase in the longwall face move duration.

Table 2

Results of the analysis of the efficiency of the longwall face move operation during the thick seams mining

Mine

Year

Longwall number-disassembling / assembling

Longwall length, m

Distance of equipment transportation, m

Depth of mining, m

Extractable seam thickness, m

Exceeding the planned deadlines for the recovery room formation, day

Total excess of planned deadlines of longwall face move, day

N 7

2014

52-07/52-09

250/250

250

220

4.3

7

2

Named after November 7

2014

13-58/13-80

290/290

2200

230

4.2

4

9

Named after A.D.Ruban

2014

804/802

200/220

3100

125

4.4

9

14

Taldinskaya-Zapadnaya-2

2014

70-08/70-09

300/300

2850

200

4.5

22

–7

N 7

2015

52-09/52-11

250-290

1800

380

4.3

10

96

Named after November 7

2015

13-78/13-58-2

280/180

1750

210

4.4

7

3

Named after November 7

2015

13-80/13-78

290/280

2340

200

4.5

6

–9

Named after A.D.Ruban

2015

802/801

200/220

3100

90

4.4

9

46

Kotinskaya

2015

52-09/52-10

280/200

4200

330

4.3

24

100

Named after November 7

2016

13-58-2/13-85

180/240

4100

120

4.5

–5

–10

Named after November 7

2016

13-85/13-86

240/290

600

100

4.6

–3

–12

Kotinskaya

2016

52-10/50-02

300/400

7000

330

4.3/3.7

6

15

Taldinskaya-Zapadnaya-1

2016

66-06/66-05

300/300

1600

120

4.5

18

131

Named after V.D.Yalevskiy

2017

50-02/50-03

400/400

2600

105

3.7

–8

72

Named after V.D.Yalevskiy

2017

52-10/52-13

300/180

3300

280

4.3

0

30

Taldinskaya-Zapadnaya-1

2017

66-05/66-08

300/300

2800

130

4.5

–1

57

Taldinskaya-Zapadnaya-2

2017

70-09/70-10

300/300

2900

180

4.5

5

26

Named after V.D.Yalevskiy

2018

50-03/50-04

400/400

2800

200

3.7

–4

127

Taldinskaya-Zapadnaya-1

2018

66-08/66-09

300/280

1800

130

4.5

6

115

Named after A.D.Ruban

2019

812/814

300/300

3800

110

4.4

47

18

Named after V.D.Yalevskiy

2019

50-04/50-05

400/400

3000

270

3.7

5

61

Named after V.D.Yalevskiy

2019

52-13/52-14-1

300/400

5500

270

4.3

6

218

A detailed analysis of cases of significant terms excess of longwall face move showed that their main cause is associated with the instability of the roof and the edge of the recovery room. Increased fallout in such cases makes it difficult to form, maintain and use the recovery room. From 2014 to 2019, the recovery room supporting was constantly improved – the transition from the use of timber-plates to roof bolting with a polymer mesh, which significantly reduced the labor intensity and increased the work safety on the recovery room formation. In complicated mining and geological conditions, there are problems with maintaining the set-up room. For example, the cross-section of the set-up room 70-09 at the Taldinskaya-Zapadnaya-2 mine decreased due to floor heaving, which required labor-intensive work on dinting and increased the longwall face move time by 22 days.

The tendency to increase the longwall length to 400 m and the longwall panel length to 4 km or more at mines with the thick coal seams (currently there are two longwalls at the mine “Named after V.D.Yalevskiy”, in the future – the Taldinskaya-Zapadnaya-2 mine, etc.), predetermined a sharp increase in the total weight and transportation distance of equipment during longwall face move. The low capacity of hanging monorails leads to an increase in the duration of longwall face move and makes it necessary to search for other technological solutions. The main direction of improving the transport system is currently considered the use of pneumatic wheeled vehicles and the transition to the three entry for panel preparation, one of which (additional) will be used for the transport of cargo, materials and equipment.

A large number of scientific papers are devoted to ensuring the operational condition of set-up and recovery rooms. The greatest attention is paid to the maintenance of recovery rooms that are affected by the bearing pressure of longwall [3, 7, 13], since the set-up room does not have such an influence and, as a result, is operated in more favorable conditions. There are two main directions for ensuring the operational condition of the recovery rooms, based on the choice of a rational place for their formation by the longwall face equipment: 1) the location of the recovery room directly behind the fracture crack of the main roof to minimize the bearing pressure in its vicinity [15, 17]; 2) the location of the recovery room outside the zones of increased rock pressure from the edge parts and the pillars formed on the converged coal seams. The development of converged coal seams is characterized by a significant impact not only on the recovery rooms condition, but also on any entries on the longwall panels [19, 23, 33], especially those that are also in the influence zone of longwall operations carried out on the developed seam [12, 14, 20].

The technology of recovery room forming behind a fracture crack, which is described in detail in [16], deserves attention. The proposed method makes it possible to predict the step of the main roof caving and ensures the recovery room formation directly behind the collapse crack of the main roof, minimizing the load on the edges and roof of the recovery room and allowing, as experience shows, to significantly reduce labor costs and the disassembling time when working out medium-thickness coal seams [15-17].

When mining of converged coal seams with the leaving of non-destructible coal pillars between the longwall panels, stress shadow zones (SSZ) are formed, in which the level of the roof displacement of the workings can increase by 2-3 times. Also, the level of displacement in the roof of workings in the SSZ zones from the edge parts of the rock mass can increase approximately twice. When mining the converged coal seams, the set-up and recovery rooms are most often located in the immediate vicinity of the edge parts of the rock mass formed along the converged coal seam. The analysis of foreign experience shows the need to shift the set-up and recovery rooms under the gob by 30 m or more. The current tendency to increase the longwall panels sizes [8, 9, 26] complicates such a link between the work on the converged seams [25, 32]. To ensure the operational condition of the workings of the converged seams, it is recommended that they be located with an offset under the gob [18, 21, 24]. However, the location of all workings under the gob is possible only with the scheme of interconnection of work on seams (Fig.1). Taking into account that the descending order of development is the most rational for converged seams with the leaving of non-destructible pillars (especially when mining thick seams), such a scheme can be recommended for widespread use in the mines of Kuzbass. The features of the proposed scheme are the preparation of the longwall panels using three entries, which ensures an increase in the efficiency of methane release and transport management at the working area. The main parameters of the scheme are: the longwall panel length and width, the width of the pillars, the value of the displacement Z of the entries of the lower seam relative to the edge part of the upper seam rock mass, the value of the displacement X of the set-up room relative to the set-up room of the upper seam, the value of the displacement Y of the recovery room relative to the recovery room of the upper seam. As a disadvantage of the presented scheme, it should be noted that the use of the scheme limits the longwall panel length along the underlying seam. To eliminate this drawback, it is possible to locate the set-up and (or) recovery rooms of the previously abovemined (undermined) seam under the edge parts of the mass of the working seam at a distance exceeding the width of the bearing pressure zone. This approach ensures that the recovery room is located outside the zone of influence of increased stresses from the edge part of the rock mass.

Method of conducting numerical studies

To justify the parameters of the presented scheme, numerical studies were performed using the finite element method. The developed three-dimensional model of the rock mass (Fig.2) included two coal seams, rocks, the gobs of two longwall panels along the upper seam, the gob and the recovery room, as well as precinct entries along the lower seam.

The modeling was carried out for the part of the mined longwall panel directly adjacent to the recovery room. During the modeling, the depth of mining operations, the thickness and deformation characteristics of the interbed, the parameters X, Y, Z (see Fig.1), which determine the location of the workings of the abovemined seam relative to the edge parts and the pillars formed on the abovemined seam, were changed.

Fig.1. The recommended scheme of the workings location of the mining seam, taking into account the gobs and pillars along the overlying seam

Fig.2. Three-dimensional model of a rock mass 1 – the gob of the upper seam; 2 – the recovery room; 3 – the workings of the longwall panel; 4 – the upper seam; 5 – the lower seam; 6 – the gob of the lower seam

Discussion of the results

As an example of the obtained results, Fig.3 shows the distribution of vertical stresses: in the plane of the lower seam (Fig.3, a) and the vertical plane passing along the central part of the pillar formed between the mined out longwall panels along the upper seam (Fig.3, b). The results are presented for the following data set: depth 600 m, interbed thickness – 50 m, longwall length along the abovemined seam 300 m, width of the pillars 30 m, longwall length along the abovemined seam 400 m, width of the pillars 40 m, displacement of the recovery room under the gob 100 m.

As can be seen from Fig.3, the location of the recovery room with a significant (100 m) displacement under the gob when using the recommended scheme for the layout of workings does not exclude the formation of zones with increased stresses associated with the influence of a non-destructible inter-longwall pillar. Considering the absolute values of stresses in this zone, it can be concluded that they do not exceed the stresses that could occur in the zone of the bearing pressure of the longwall in the absence of the influence of overworking. Thus, for the situation under consideration, the stress level is not elevated, but the uneven nature of its distribution and the crucial influence of the pillar forming the SSZ should be taken into account when determining the parameters of the supporting patterns and choosing the sequence of disassembling of the the equipment. In addition, in the event of dead-end breakthroughs, their location in high-stresses zones under the pillars should be completely excluded or minimized.

Fig. 3. Fields and plots of vertical stresses in typical cross-sections of the model

Studies have shown that the interbed thickness plays a major role and, all other things being equal, determines the conditions for maintaining the set-up and recovery rooms. For the simulated mining situation, a decrease in the interbed thickness while maintaining other constant parameters leads to a significant increase in the stress level under the pillar and a deterioration in the conditions for the formation and further operation of the recovery room. To determine the rational location of the recovery room, the current regulatory document* can be used, taking into account the influence of the edge parts and pillars on the level of roof displacements in the workings fixed with roof bolting support. The calculation of the expected displacements showed that in order to ensure the operational condition of the set-up room, its displacement under the gob of the abovemined seam by 30 m is sufficient.

Conclusion

The continuous improvement of the reliability and energy-efficiency of the longwall equipment created conditions for increasing the sizes of the longwall panels (the length and width), which made it possible to reduce the number of longwall panels within the mine fields and, as a result, the number of the longwall face moves, ensuring a reduction in the cost of coal mining. However, an increase in the longwall length led to an increase in the total mass of the longwall equipment, and the panel length led to an increase in the distance of its transportation, which ultimately increased the complexity of the longwall face move operations and necessitated the improvement of the applied technological schemes and labor organization.

The conducted studies have shown that at present, the greatest complexity lies in the longwall face move operations during the mining of thick seams. Exceeding planned deadlines for the longwall face move operations at the mines of JSC SUEK-Kuzbass is on average 50 days, reaching in some cases 100-200 days. The main reasons for the lower efficiency of longwall face move operations during the mining of thick seams include: a higher mass of equipment, complex geotechnical conditions for the formation and maintenance of recovery rooms, which complicate their subsequent operation, low throughput of hanging monorails, insufficient efficiency of the technological schemes used for the longwall face move operations.

Numerical studies have shown the need to take into account the uneven distribution of stresses within the recovery room when using the recommended scheme for mining previously abovemined seams. Studies have established that the main factors determining the possibility of ensuring the operational condition of the recovery rooms are: the interbed thickness, the properties of the interbed rocks, the recovery room displacement. The recovery room shift of 50 m is sufficient to minimize the impact of abovemining and ensure its operational condition, however, when choosing the supporting parameters and the sequence of the shields extraction, taking into account the uneven distribution of stresses (due to the influence of the pillars) is a necessary condition for the effective formation and maintenance of recovery rooms in abovemined areas. The set-up room shift when using the recommended scheme (see Fig.1) should be at least 30 m.

The following measures are recommended to improve the technology and organization of the longwall face move operation during the intensive mining of flat-lying coal seams in the Kuzbass mines:

  • ensuring timely preparation of the new longwall panel due to the advanced development of panel entries and main workings;
  • ensuring the rational location of the set-up and recovery rooms chambers relative to the edge parts and pillars formed on the adjacent seams;
  • formation of the recovery room taking into account the main roof-caving increment;
  • the use of longwall bolting unit of the Hygromatik type to increase the speed of the recovery room bolting;
  • application of the three entries panel layout to improve the efficiency of transport and control of gas release at the longwall panels;
  • ensuring the advanced implementation of dead-end breakthroughs to the place of recovery room formation, creating the possibility of independent work on the equipment removal simultaneously on several sites of the recovery room;
  • implementation and wide application of pneumatic wheeled vehicles with ensuring conditions for their operation;
  • the set-up room location in the one line with the recovery room (in suitable geological and mining conditions) to reduce the distance of equipment transportation;
  • carrying out the advanced mounting of the longwall conveyor and the shearer.

The proposed recommendations will ensure a significant reduction in the timing of longwall face move operations by creating favorable conditions for the formation and maintenance of recovery rooms, timely preparation of a new longwall panel, the use of modern transport equipment and the organization of longwall face move operations.


*Federal norms and rules in the field of industrial safety: Instructions for the calculation and use of anchor supports in coal mines. Series 05. 2015. Iss. 42, p. 186.

References

  1. Gendler S.G., Nguen T.K. Justification of rational methods for provision of air to faces of operating coal mines of vietnam during deepening of mining. Journal of Mining Institute. 2018. Vol. 234, p. 652-657. DOI: 10.31897/pmi.2018.6.652
  2. Kazanin O.I., Sidorenko А.А., Meshkov А.А. Organizational and technological principles of realization of the modern high productive longwall equipment capacity. Ugol. 2019. N 12, p. 4-13. DOI: 10.18796/0041-5790-2019-12-4-13
  3. Kozlov A.V., Teslya A.B., Chzhan S. Principles of assessment and management approaches to innovation potential of coal industry enterprises. Journal of Mining Institute. 2017. Vol. 223, p. 131-138. DOI: 10.18454/pmi.2017.1.131
  4. Kopylov K.N., Kubrin S.S., Reshetnyak S.N. The importance of improving energy efficiency and safety of coal mine extraction area. Ugol. 2018. N 10, p. 66-70. DOI: 10.18796/0041-5790-2018-10-66-70 (in Russian).
  5. Meshkov A.A., Volkov M.A., Ordin A.A. et al. On record length and productivity of highwall mining the V.D.Yalevsky mine. Ugol. 2018. N 7, p. 4-7. DOI: 10.18796/0041-5790-2018-7-4-7 (in Russian).
  6. Meshkov A.A., Popov A.L., Popova Yu.V.et al. Prediction of hazardous phenomena within operating coal seam for the Yalevsky mine field. Mining informational and analytical bulletin.2020. N 2, p. 22-23. DOI: 10.25018/0236-1493-2020-2-0-22-33 (in Russian).
  7. Slastunov S.V., Yutyaev E.P. Justified selection of a seam degassing technology to ensure safety of intensive coal mining. Journal of Mining Institute. 2017. Vol. 223, p. 125-130. DOI: 10.18454/pmi.2017.1.125
  8. Chemezov E.N. Industrial safety principles in coal mining. Journal of Mining Institute. 2019. Vol. 240, p. 649-653. DOI: 10.31897/PMI.2019.6.649
  9. Yutyaev E.P. Present-day challenges and prospects of flat gas containing coal beds underground mining technology. Ugol. 2017. N 5, p. 30-36. DOI: 10.18796/0041-5790-2017-5-30-36
  10. Stebnev A.V., Muchortikov S.G., Zadkov D.A., Gabov V.V. Analysis of operation of powered longwall systems in mines of SUEK-Kuzbass. Eurasian mining. 2017. N 2, p. 28-32.
  11. Hanson B., Ochsner R., Stankus J.C. et al. A Case Study of a Low Overburden Longwall Recovery with Pre-Developed Recovery Entries. 33rd International Conference on Ground Control in Mining, 29-31 July, 2014, Morgantown, USA. ICGCM, 2014. Vol. 33, p. 1-8.
  12. Du X. Field measurements of overburden strata deformation response to longwall mining. Proceedings of the 37th International Conference on Ground Control in Mining, ICGCM 2018, 28-30 June, 2018, Sarawak, Malaysia. ICGCM, 2018, p. 71-82.
  13. Gearhart D.F., Jones T.H., Compton C.S. Ground response as a longwall advances into a backfilled recovery room under low cover. 33rd International Conference on Ground Control in Mining, 29-31 July, 2014, Morgantown, USA. ICGCM, 2014. Vol. 33, p. 25-35.
  14. Yuan R., Du F., Song C., Song G., QiaoQ. In-site monitoring and analysis on overburden movements for multiple seam mining using longwall caving method. Journal of Mining and Safety Engineering. 2018. Vol. 35. Iss. 4, p. 717-724. DOI: 10.13545/j.cnki.jmse.2018.04.008
  15. Karpov G.N.,LeisleA.V. Qualitative assessment of strain stress distribution of rock massif in the vicinity of pre-driven recovery room. Journal of Industrial Pollution Control. 2017. Vol. 33. Iss. 1, p. 840-846.
  16. Klimov V.V. Geomechanical feasibility of underground coal mining technology using control systems of electro-hydraulic shield supports for longwall mining. International Conference on Mechanical Engineering, Automation and Control Systems, 12-14 December, 2018, Novosibirsk, Russian Federation. IOP Conference Series: Materials Science and Engineering, 2019. Vol. 560. N 012067. DOI: 10.1088/1757-899X/560/1/012067
  17. Kovalsk E.R.,Karpov G.N., LeisleA.V. Investigation of underground entries deformation mechanisms within zones of high stresses. International Journal of Civil Engineering and Technology. 2018. Vol. 9. Iss. 6, p 534-543.
  18. Longwall production remains steady. Coal Age. January/February 2020, p. 16-24. URL: https://www.coalage.com/flipbooks/january-february-2020 (date of access 15.01.2021).
  19. Mark C. An updated empirical model for ground control in U.S. Multiseam coal mines. International Journal of Mining Science and Technology. 2021. Vol. 31. Iss. 2, p. 163-174. DOI: 10.1016/j.ijmst.2020.12.024
  20. Mark C., AgioutantisZ. Analysis of coal pillar stability (ACPS): A new generation of pillar design software. International Journal of Mining Science and Technology. 2019. Vol. 29. Iss. 1, p. 87-91. DOI: 10.1016/j.ijmst.2018.11.007
  21. Mark C., Chase F.E., Pappas D.M. Multiple-seam mining in the United States: design based on case histories. Proceedings on the New Technology for Groung Control in multiple seam mining. 2007, p. 15-27.
  22. Nguyen K.L.,Gabov V.V., Zadkov D.A. Improving efficiency of cleanup and coal flow formation on conveyor by shearer loader with accessorial blade. Eurasian Mining. 2019. N 1, p. 37-39. DOI: 10.17580/em.2019.01.09
  23. Nikiforov A.V., Vinogradov E.A., Kochneva A.A. Analysis of multiple seam stability. International Journal of Civil Engineering and Technology. 2019. Vol. 10. Iss. 2, p. 1132-1139.
  24. Wu G., Fang X., Bai H. et al. Optimization of roadway layout in ultra-close coal seams: A case study. PLoS ONE. 2018. Vol. 13. Iss. 11. DOI: 10.1371/journal.pone.0207447
  25. Palyanova N.V., Zadkov D.A., Chubukova S.G. Legal framework for the sustainable economic and ecological development in the coal industry in Russia. Eurasian Mining. 2017. N 1, p. 3-5. DOI: 10.17580/em.2017.01.01
  26. Peng S.S. Longwall mining. CRC Press, 2019, p. 562. DOI: 10.1201/9780429260049
  27. Kazanin O.I., Sidorenko A.A., Meshkov A.A., Sidorenko S.A. Reproduction of the longwall panels: Modern requirements for the technology and organization of the development operations at coal mines. Eurasian Mining. 2020. N 2, p. 19-23.DOI: 10.17580/em.2020.02.05
  28. Zuev B.Yu., Istomin R.S., Kovshov S.V., Kitsis V.M. Physical modeling the formation of roof collapse zones in Vorkuta coal mines. Bulletin of the Mineral Research and Exploration. 2020. Vol. 162, p. 225-234. DOI: 10.19111/bulletinofmre.620478
  29. Reshetnyak S., Bondarenko A. Analysis of Technological Performance of the Extraction Area of the Coal Mine. 3rd International Innovative Mining Symposium, 3-5 October, 2018, Kemerovo, Russian Federation. E3S Web of Conferences, 2018. Vol. 41. N 01014. DOI: 10.1051/e3sconf/20184101014
  30. Rudakov M., Gridina E., Kretschmann J. Risk-based thinking as a basis for efficient occupational safety management in the mining industry. Sustainability. 2021. Vol. 13. Iss. 2. N 470, p. 1-14. DOI: 10.3390/su13020470
  31. Rudakov M.L., Kolvakh K.A., Derkach I.V. Assessment of environmental and occupational safety in mining industry during underground coal mining. Journal of Environmental Management and Tourism. 2020. Vol. 11. Iss. 3 (43), p. 579-588. DOI: 10.14505/jemt.v11.3(43).10
  32. Suchowerska A.M. Geomechanics of single seam and multi-seam longwall coal mining: PhD thesis. University of Newcastle, Australia, 2014, p. 268.
  33. Zhu W., Xu J., Xu G. Mechanism and control of roof fall and support failure incidents occurring near longwall recovery roadways. Journal of the Southern African Institute of Mining and Metallurgy. 2017. Vol. 117. Iss. 11, p. 1063-1072. DOI: 10.17159/2411-9717/2017/v117n11a11

Similar articles

Improving the efficiency of autonomous electrical complexes of oil and gas enterprises
2021 Boris N. Abramovich, Ivan A. Bogdanov
Developing features of the near-bottomhole zones in productive formations at fields with high gas saturation of formation oil
2021 Vladislav I. Galkin, Dmitry A. Martyushev, Inna N. Ponomareva, Irina A. Chernykh
Transition between relieved and unrelieved modes when cutting rocks with conical picks
2021 Evgenii A. Averin, Aleksandr B. Zhabin, Andrey V. Polyakov, Yurii N. Linnik, Vladimir Yu. Linnik
Increasing the efficiency of technological preparation for the production of the manufacture components equipment for the mineral resource complex
2021 Irina N. Khrustaleva, Sergei A. Lyubomudrov, Tatyana A. Larionova, Yana Y. Brovkina
The influence of solar energy on the development of the mining industry in the Republic of Cuba
2021 Yaroslav E. Shklyarskiy, Daniel Díaz Guerra, Emiliia V. Iakovleva, Anton Rassõlkin
Cadastral valuation of forest lands, taking into account the degree of development of their infrastructure
2021 Vasily F. Kovyazin, Anastasia A. Kitcenko, Seyed Omid Reza Shobairi