Submit an Article
Become a reviewer
Vol 58 Iss. 1
Pages:
145-149
Download volume:
RUS
Article

Experience of inter-chamber pillar mining after consolidation of the primary chambers' backfill

Authors:
Yu. L. Minaev
A. V. Karpunin
A. G. Vasiliev
Date submitted:
1968-07-28
Date accepted:
1968-09-07
Date published:
1969-05-05

Abstract

In 1966 at the Kaula-Kotselvaara mine of the Pechanganickel Combine, experimental work was carried out on the development of an inter-chamber pillar located between the walls of the cement-reinforced backfill. Pilot works were carried out in a 6-8 m thick section of the ore body with a dip angle of 26-30°. The intervening rocks - phyllites - are partially broken by transverse fractures. In general, the ore and rock are stable. Ore strength coefficient is 8-12, rock strength coefficient is 10-12. Volume weight of the ore is 3.2 t/m3 and of the embedding material is 2.8 t/m3.

Область исследования:
(Archived) Without section
Funding:

None

Go to volume 58

Similar articles

Prof. Vladimir N. Semevsky (1898-1968)
1969 A. I. Shablygin, N. Z. Galaev, Yu. I. Panenkov
Computer-aided selection of optimal parameters of blocks in caving development
1969 A. A. Kavtaskin
To the question of underground horizons insulation at mines of Apatit Combine
1969 O. N. Rusak, Yu. N. Nikolaev
Depth of ore deposits development by open-cutting systems
1969 A. B. Makeenkov
Calculation of limit spans of unshored frozen roofs
1969 Yu. V. Shuvalov
Causes of losses of broken ore at Apatitovy mine
1969 Yu. N. Nikolaev, V. V. Shchipachev