Submit an Article
Become a reviewer
Vol 58 Iss. 1
Pages:
145-149
Download volume:
RUS
Article

Experience of inter-chamber pillar mining after consolidation of the primary chambers' backfill

Authors:
Yu. L. Minaev
A. V. Karpunin
A. G. Vasiliev
Date submitted:
1968-07-28
Date accepted:
1968-09-07
Date published:
1969-05-05

Abstract

In 1966 at the Kaula-Kotselvaara mine of the Pechanganickel Combine, experimental work was carried out on the development of an inter-chamber pillar located between the walls of the cement-reinforced backfill. Pilot works were carried out in a 6-8 m thick section of the ore body with a dip angle of 26-30°. The intervening rocks - phyllites - are partially broken by transverse fractures. In general, the ore and rock are stable. Ore strength coefficient is 8-12, rock strength coefficient is 10-12. Volume weight of the ore is 3.2 t/m3 and of the embedding material is 2.8 t/m3.

Область исследования:
(Archived) Without section
Go to volume 58

Similar articles

Excavation of barrier pillars during mining of ore fields by caving systems
1969 N. Z. Galaev
Computer-aided selection of optimal parameters of blocks in caving development
1969 A. A. Kavtaskin
Investigation of bearing pressure at different order of block excavation in a floor (for conditions of mining of lower horizons of Kirovsky mine of Apatit Combine)
1969 N. Z. Galaev, G. G. Milekhin
On directions of development of technology of underground development of ore deposits
1969 V. N. Semevsky
Prof. Vladimir N. Semevsky (1898-1968)
1969 A. I. Shablygin, N. Z. Galaev, Yu. I. Panenkov
Calculation of limit spans of unshored frozen roofs
1969 Yu. V. Shuvalov