Experience of inter-chamber pillar mining after consolidation of the primary chambers' backfill

Authors:
Yu. L. Minaev
A. V. Karpunin
A. G. Vasiliev
Date submitted:
1968-07-28
Date accepted:
1968-09-07
Date published:
1969-05-05

Abstract

In 1966 at the Kaula‑Kotselvaara mine of the Pechenganikel Combine, experimental work was carried out on the development of an inter‑chamber pillar located between the walls of cement‑reinforced backfill. Pilot works were carried out in a 6‑8 m thick section of the ore body with a dip angle of 26‑30°. The host rocks – phyllites – are partially broken by transverse fractures. In general, the ore and rock are stable. The strength coefficient of the ore is 8‑12, of the rock – 10‑12. Bulk density of the ore is 3.2 t/m³, of the backfill material – 2.8 t/m³.

Область исследования:
(Archived) Without section
Funding:

None

Go to volume 58

Similar articles

Rational application area of vibratory ore discharge at Apatit Combine
1969 Yu. A. Korotkov
Prof. Vladimir N. Semevsky (1898-1968)
1969 A. I. Shablygin, N. Z. Galaev, Yu. I. Panenkov
To On the question of underground thermal insulation of horizons insulation at the mines of the Apatit Combine
1969 O. N. Rusak, Yu. N. Nikolaev
Investigation of the stressed state of pillars under the chamber-pillar system of development at the Mayak mine
1969 V. D. Paliy, Yu. D. Orlov, V. P. Ushenin
Economic assessment of damage from losses and dilution during development of rich ores
1969 P. G. Makulov
Mining excavations by pre-slotting method
1969 V. V. Sychev