Reconstruction of vertical shaft of Uzelginsky mine

Authors:
D. E. Zhurov
About authors
  • Shakhty Institute of South Russian State Technical University (Novocherkassk Polytechnic Institute)
Date submitted:
2008-08-17
Date accepted:
2008-10-27
Date published:
2009-03-20

Abstract

The paper studies details of the draft plan for skip shaft reconstruction at the Uzelginsky Ore Mine. Methods of loading chamber construction at the –340 m horizon and improvement of the shaft lining at the construction level are given a detailed description of.

Область исследования:
(Archived) Geodesy, geomechanics and underground construction
Go to volume 181

Similar articles

Development of the device and technology of diagnostics of anchoring of rocks and building structures
2009 E. A. Voznesensky
Justification of parameters and design of auger loader of tunneling-cleaning combine
2009 D. A. Sidyakin
Justification of the parameters of the chamber and pillar system of development during the mining of declivity coal seams
2009 V. A. Shuklin
Influence of blast waves on the stressed state of the barrier pillar at carrying out of parallel excavations
2009 Yu. N. Antonov
Organization of mining works at preparation of new horizons at watered open pits
2009 I. I. Dudanov, V. S. Avraamov, D. N. Ligotsky, G. A. Kholodnyakov
Improvement of economic evaluation of investment projects in oil and gas industry
2009 A. V. Aprelova