Justification of the parameters of the chamber and pillar system of development during the mining of declivity coal seams

Authors:
V. A. Shuklin
About authors
  • Kuzbass State Technical University
Date submitted:
2008-08-25
Date accepted:
2008-10-11
Date published:
2009-03-20

Abstract

The paper offers analysis of selected parameters for room-and-pillar mining system basing on in-situ tests in mining of 6-6A Strata at the Raspadskaya Mine.

Область исследования:
Mining
Go to volume 181

Similar articles

Peculiarities of maintenance of preparatory workings in the zones of increased mining pressure
2009 A. V. Rogachkov
Organization of mining works at preparation of new horizons at watered open pits
2009 I. I. Dudanov, V. S. Avraamov, D. N. Ligotsky, G. A. Kholodnyakov
Justification of reliability of cantilever-rope reinforcement of deep shafts
2009 D. A. Kotikov
Method of research of influence of deposit eccentricity on minimum current stripping volumes
2009 A. V. Polovinko, G. A. Kholodnyakov, D. G. Kholodnyakov
Jaw crusher of double crushing
2009 A. I. Dashkevich
Types of metasomatites of the Buruktalskoye deposit of hypergene nickel-lead ores, Southern Urals
2009 S. O. Ryzhkova