Perfection of shutters for ore chutes
About authors
- 1 — Ph.D., Dr.Sci. Saint Petersburg State Mining Institute (Technical University)
- 2 — Student Saint Petersburg State Mining Institute (Technical University)
Abstract
The construction of a chain shutter for use on mines is described and proved at release of large pieces of mined rock from final apertures of ore chutes of the increased cross-section sections, allowing to eliminate lacks of existing constructions and to raise reliability of operation the chute tapper of unloading of mined rock.
Область исследования:
(Archived) Geotechnical engineering, powerengineering and automation
Funding:
None
References
- RF 2008145794 appl., IPC E 21 F 13/00. The stand for research of parameters of chain shutter for shutter / J.D. Tarasov, I.V.Ushatinsky. Subm. 19.11.2008.
- RF Patent 2347077, IPC E 21 F 13/00, B65 G 90/54. Chain shutter/ J.D.Tarasov. Subm. 11.07.2007. Pubd. 20.02.2009; Bul. № 9.
- Tarasov J.D. Transport machines of continuous action/ Saint Petersburg states mining institute. Saint Petersburg, 2009. 144 р.
Similar articles
Complex geological engineering and geoenvironmental monitoring as a basis for creation of strategy of Saint Petersburg architectural and historical monuments conservation
2010 A. V. Shidlovskaya
Geomechanical substantiation of parameters of the fastening of railway tunnels in the conditions of the North Caucasus
2010 N. A. Belyakov