Analysis of tunnel induced settlement due to tunnel development with a help of TBM is given in current article. Surface settlement trough and settlement profile in longitudinal and transverse directions is shown below. A brief analysis of semi-empirical method of tunnel induced settlement calculation and determination of strains around excavation is given. Volume loss is given based on the in-situ observation.
Область исследования:
(Archived) Geomechanics
Similar articles
Substantiation of rational mining parameters for iv potash horizon of the starobin potash deposit
2011 O. V. Kovalev, S. P. Mozer, I. Yu. Mozer, A. V. Leisle
Dynamic radiation control methods and instruments application peculiarities at underground points for nuclear materials storage placement, radioactive waste storages and underground nuclear thermo power plants
2011 V. G. Kondratev