Determination of the front mining length for backfill mining method of complex structure carbon deposits by railway transport

Authors:
V. V. Ivanov
About authors
  • Saint Petersburg State Mining Institute (Technical University)
Date submitted:
2010-08-14
Date accepted:
2010-10-22
Date published:
2011-04-05

Abstract

The work describes basic features of open pit development of complex structure carbon deposits. The rational length of excavator block for different models of dragline for backfill mining method was determined. The work also gives the dependence for determining the production front length for development of complex structure carbon deposits with the use of railway service for transportation of the extracted mineral.

Область исследования:
(Archived) Geotechnology
Go to volume 190

Similar articles

Mathematical modelling of geomechanical processes at the estimation of influence of building underground constructions in cities on the undermined rock mass
2011 E. M. Volokhov, D. A. Potemkin
Calculation of displacement and deformations of rocks tunnels arising at building taking into account vertical asymmetry in distribution of displacement
2011 E. M. Volokhov, N. S. Bakh
Management stress-strain state block structure partition arrays in difficult geological and mining engineering conditions of mine Тalnakh
2011 V. A. Zvezdkin, V. N. Karelin, A. G. Anokhin, Yu. N. Nagovitsin
A new technique for the determination of ultimate strength in extention of rocks
2011 V. A. Korshunov, Yu. M. Kartashov
The method of planning of stockpiles laser scanner mine surveying
2011 E. A. Nesterenko
Open cast technological system with in-pit fully mobile crushing reliability avaluation
2011 S. I. Fomin, A. A. Faul, A. I. Ponomarev