Determination of the front mining length for backfill mining method of complex structure carbon deposits by railway transport

Authors:
V. V. Ivanov
About authors
  • Saint Petersburg State Mining Institute (Technical University)
Date submitted:
2010-08-14
Date accepted:
2010-10-22
Date published:
2011-04-05

Abstract

The work describes basic features of open pit development of complex structure carbon deposits. The rational length of excavator block for different models of dragline for backfill mining method was determined. The work also gives the dependence for determining the production front length for development of complex structure carbon deposits with the use of railway service for transportation of the extracted mineral.

Область исследования:
(Archived) Geotechnology
Funding:

None

Go to volume 190

Similar articles

Connection between lumpiness and block size оf mined rock from photographs using computer processing research
2011 A. P. Sannikova
The engineering geological control of underground transport tunnels exploitation reliability in Saint Petersburg
2011 R. E. Dashko, P. V. Kotyukov
Technology of «cold» briquetting of rich ores of the Jakovlevsky deposit
2011 V. L. Trushko, R. E. Dashko, V. B. Kuskov, A. S. Klyamko
Qiuck-acting technique for the determination of rheological properties of rocks
2011 M. D. Ilinov, Yu. M. Kartashov
Foundation of Cholodninskoye deposit mining systems in conditions of ecological risks
2011 V. P. Zubov, O. V. Mikhailenko, A. A. Antonov, M. D. Morozov
Assessment of geodynamic and geomechanical conditions in the mining of ore bodies of near-ore bank reserves at the Koashva open-pit mine
2011 V. V. Zubkov, I. A. Zubkova, G. V. Leontev, A. G. Zileev