Determination of the front mining length for backfill mining method of complex structure carbon deposits by railway transport
Authors:
About authors
- Saint Petersburg State Mining Institute (Technical University)
Abstract
The work describes basic features of open pit development of complex structure carbon deposits. The rational length of excavator block for different models of dragline for backfill mining method was determined. The work also gives the dependence for determining the production front length for development of complex structure carbon deposits with the use of railway service for transportation of the extracted mineral.
Область исследования:
(Archived) Geotechnology
Funding:
None
Similar articles
Connection between lumpiness and block size оf mined rock from photographs using computer processing research
2011 A. P. Sannikova
The engineering geological control of underground transport tunnels exploitation reliability in Saint Petersburg
2011 R. E. Dashko, P. V. Kotyukov
Technology of «cold» briquetting of rich ores of the Jakovlevsky deposit
2011 V. L. Trushko, R. E. Dashko, V. B. Kuskov, A. S. Klyamko
Qiuck-acting technique for the determination of rheological properties of rocks
2011 M. D. Ilinov, Yu. M. Kartashov