The simulation modelling in deposit project development analysis on the base of Shaidomskoe building stone deposit, «Amphibolithoviy» mining field
About authors
- 1 — Ph.D., Dr.Sci. professor Saint Petersburg State Mining University
- 2 — post-graduate student Saint Petersburg State Mining University
Abstract
The article covers the approach to the development project probabilistic estimation of building stone deposit. The approach is based on the Monte-Carlo simulation modelling of its efficiency indicators. Also the correlation and statistical analysis of simulation are conducted.
Область исследования:
(Archived) Economical problems in use of subsurface and development of the mineral resources complex
References
- Ampilov Y.P., Gert A.A. Economic geology. Мoscow, 2006. 409 p.
- Astahov A.S., Goldman E.L. Economics for geologists and economists. Мoscow, 2007. 328 p.
- Vadzinsky R. Statistical computation in MS Excel. Saint Petersburg, 2008. 608 p.
- Mamiy E.A., Baiburtian M.A. Approach to the development of risk analysis method. URL: http://www.cfin.ru/finanalysis/risk/innovative.shtml
- Sobol I.M. Monte-Carlo method. Мoscow, 1978 . 64 р.
Similar articles
The administrative contract as the mechanism оf perfection of economic-legal forms and methods in subsoil use
2011 D. R. Kayumov
Overview of the main risks of the enterprises of mining and metallurgical branches in modern conditions
2011 A. Yu. Tsvetkova
Domanikoid formations of siberian platform – kuonamskaya bituminous carbonate-shale formation
2011 V. B. Archegov