Particularities of gold ore deposit development in complex environment

Authors:
V. A. Bakhtin1
L. I. Boguslavskaya2
S. V. Kiryukov3
E. N. Kozlov4
T. A. Prolomova5
A. D. Fomenko6
About authors
  • 1 — deputy head of mining board for open-cut min CJSC «Saint Petersburg Mining Project and Engineering Company»
  • 2 — chief engineering manager CJSC «Saint Petersburg Mining Project and Engineering Company»
  • 3 — Ph.D. director in projects development CJSC «Saint Petersburg Mining Project and Engineering Company»
  • 4 — Ph.D. deputy head of mining board for underground mining CJSC «Saint Petersburg Mining Project and Engineering Company»
  • 5 — Ph.D. chief specialist in open-cut mining CJSC «Saint Petersburg Mining Project and Engineering Company»
  • 6 — chief engineer of design engineering directorate CJSC «Saint Petersburg Mining Project and Engineering Company»
Date submitted:
2011-10-18
Date accepted:
2011-12-09
Date published:
2012-11-19

Abstract

Review of the design experience in the open-cut development of a very large gold ore steeply pitching deposit are given. Complicating factors are previous underground workings and pressure subpermafrost waters. Opening of depth horizons by ore and rock incline conveyor shafts. Crushing of ore and rock in an open-pit mine before they are delivered to conveyors by semi-mobile crushers. Water depression by ring-type workings with transportation of the collected water by conveyor shafts.

Область исследования:
(Archived) Innovation activity and advances for higher efficiency of production ad plants оf mining-metallurgical complex
Keywords:
o pen- cut mine previous underground workings pressure subpermafrost waters incline conveyor shafts cyclical-and -continuous method semi-mobile crushers motor transport
Funding:

None

Go to volume 198

Similar articles

To the question of maintenance of permanent workings ventilation-waste floor in techtonic stressed zones «Big Gorst» of «Taimyr» mine
2012 V. A. Zvezdkin, V. N. Karelin, T. S. Mushtekenov
Experience in application of geophysical methods for stress-strain state of rock mass control with the goal of altering design solutions in liquidation the flooding of the emergency section of mine № 1-5 of the Barentsburg coal deposit
2012 M. V. Shvankin, S. N. Mulev, A. P. Skakun, E. N. Rabota
Optimization of drainage systems of developed and perspective polymetallic deposits of Leninogorsky area of Rudniy Altai
2012 V. B. Kolpakov
Safety problems of mining operations in high-stress hard rock massif
2012 A. A. Kozyrev, V. I. Panin, Yu. V. Fedotova
Peculiarities of prof. S.D.Korobov’s algorithm appliance in open-pit boundaries determination and mining operation regime justification
2012 A. L. Bilin
Substantiation of techniques and methods of technogeneous deposits forming represented by rock refuse and waste rock dumps at open pit mining
2012 S. P. Reshetnyak, A. V. Arkhipov