Article

Valuation of sustainable of pit wall

Authors:
M. G. Mustafin1
A. P. Sannikova2
P. I. Yushmanov3
About authors
  • 1 — Ph.D., Dr.Sci. professor National Mineral Resources University (Mining University)
  • 2 — post-graduate student National Mineral Resources University (Mining University)
  • 3 — post-graduate student National Mineral Resources University (Mining University)
Date submitted:
2011-10-15
Date accepted:
2011-12-29
Date published:
2012-11-19

Abstract

This article respond the question about using the digital photographic data in open-cast mine for specification of structural easing factor and his application for modeling of stsbility in open-cast mines with «Phase2» and «NEDRA».

Область исследования:
(Archived) Innovation in designing of mining plants
Keywords:
mines rocks stress condition pit wall bank stability of a pit wall photo durability model of a pit wall
Go to volume 198

References

  1. Balashov I.V. Deformation and Fracture of rock masses. М.: Nedra, 1988. 271 p.
  2. Mustafin M.G. Geomechanical model of the «gener a-tion – the host rocks» system and its use in predicting the dy-namic manifestations of rock pressure // Mining Geomechan-ics and Mine Servey / VNIMI. Saint Petersburg, 1999. P.93 -98.
  3. Mustafin M.G., Petuhov I.M. The mechanism of frac-ture energy and lasting layer of the soil preparatoryworkings // Mining information and analytical bulletin. Moscow: MMSU, 2002. N 10. C. 36- 41.
  4. Sannikova A.P. Connection between lumpiness and block size of mined rock from photographs using computer processing research // Proceedings of Mining Institute. 2011. Vol . 190. P.301-303.

Similar articles

Particularities of gold ore deposit development in complex environment
2012 V. A. Bakhtin, L. I. Boguslavskaya, S. V. Kiryukov, E. N. Kozlov, T. A. Prolomova, A. D. Fomenko
Mechanizаtion of steep thick coal seams working
2012 L. F. Kozhukhov, K. V. Struk
Reflectionless observation technique of deforming edges of open-pit mines and spoil dumps
2012 P. V. Koltsov
Advanced concentration technology of phosfatic- bearing ore of Oleniy ruchey deposit (Kola peninsula)
2012 V. I. Beloborodov, I. B. Zakharova, G. P. Andronov, N. M. Filimonova
Interaction between seismic activity in Kuzbass and open-pit operations
2012 S. V. Tsirel, A. A. Pavlovich
Experience in application of geophysical methods for stress-strain state of rock mass control with the goal of altering design solutions in liquidation the flooding of the emergency section of mine № 1-5 of the Barentsburg coal deposit
2012 M. V. Shvankin, S. N. Mulev, A. P. Skakun, E. N. Rabota