To study stochastic mining technical systems of opencast mines, where parallel to clearly defined values random and indefinite factors operate, probabilistic and statistical techniques are mostly used nowadays. Formally, the task of producing a design solution may, under the conditions of indeterminacy be transformed into an equivalent deterministic problem formulated for a risky situation. Uncertainty in the initial mining, geological and technical-economic information available during the design stage may result in changing the principal output characteristics of the opencast mine and undermine its operational efficiency during its exploitation. Lowering the possible economic losses is then possible via designing a stable technological  system. To minimize the degree of indeterminacy one first of all needs to identify the area of potential risk, define the probability of its emergence and assess its potential consequences. In case such consequences may be precluded, a clearer more complete understanding of the problem would promote a better thought through reaction to potential risk in the course of implementing design solutions.

10.18454/pmi.2016.5.644
Go to volume 221

References

  1. Арсентьев А.И. Производительность карьеров / Санкт-Петербург. горный ин-т им. Г.В.Плеханова (техн. ун-т). СПб, 2002. 85 с.
  2. Ганицкий В.И. Менеджмент горного производства: Терминологический словарь. М.: Горная книга, 2013. 472 с.
  3. Ларин Н.С. Управление технико-экономическими показателями карьеров нерудных строительных материалов на основе аналогового метода оценки затрат // Горный информационно-аналитический бюллетень. 2015. № 5. С.108-113.
  4. Липсиц И.В. Экономика: Учеб. для вузов. М.: ОМЕГА-Л, 2006. 656 с.
  5. Салманов О.Н. Об оптимальных сроках отработки месторождений в условиях рыночной модели экономики // Горный журнал. 1993. № 6. С.9-11.
  6. Трубецкой К.Н. Проектирование карьеров: Учеб. для вузов: В 2 т. / К.Н.Трубецкой, Г.Л.Краснянский, В.В.Хронин. М.: Изд-во Академии горных наук, 2001. Т.1. 519 с.
  7. Фомин С.И. Анализ спроса на рынке минерального сырья при определении производительности карьеров // Горный журнал. 2002. № 4. С.48-53.
  8. Фомин С.И. Оценка влияния рыночных факторов на производительность карьеров / С.И.Фомин, М.В.Баженов // Горный журнал. 1996. № 11-12. С.28-30.
  9. Фомин С.И. Оценка риска принятия решений при проектировании карьеров / С.И.Фомин, А.С.Семенов // Записки Горного института. 2007. Т.173. С.56-60.
  10. Фомин С.И. Оценка эффективности инвестирования открытой разработки сложноструктурных месторождений / С.И.Фомин, П.Б.Кава // Горный информационно-аналитический бюллетень. 2011. № 5. С.312-316.
  11. Фомин С.И. Оценка эффективности принятия проектных решений / С.И.Фомин, Д.В.Пасынков, А.С.Семенов // Записки Горного института. 2009. Т.180. С.12-15.
  12. Фомин С.И. Производительность карьеров и спрос на минеральное сырье. СПб: Тема, 1999. 169 с.
  13. Camus J.P. Management of mineral resources // Mining Engineering (SME). 2002. January. P.17-25.
  14. DeMarzo Peter M. Corporate Incentives for Hedging and Hedge Accounting / Peter M. DeMarzo; Darrell Duffie // The Review of Financial Studies. 1995. Vol.8. N 3. P.743-771.
  15. Fomin S.I. Risk analysis method for opencast mining project // Annual. University of mining and geology St. Ivan Rilski. Sofia. 2012. Part 2. Vol.55. P.23-28.
  16. Frizell E.M. USBM designs inpit movable crusher based on mine personnel survey / E.M.Frizell, R.W.Utley // Mining Engineering. 1983. Vol.35. N 4. P.317-321.
  17. Hill J.H. Geological and economical estimate of mining projects. London: Informa Group, 1993. 85 p.
  18. Hustrulid W. Open Pit Mine: Planning & Design / W.Hustrulid, M.Kuchta. Rotterdam; Brookfield, VT: A.A.Balkema, 1998. 735 p.
  19. Open Pit Mining Planning by William A. Hustrulid, Mark E. Kuchta. CRC Press, Har/Com edition. 2006. 971 p.
  20. Schröder D.L. Large surface miners – applications and cost calculations // Krupp Fördertechnik GmbH, Essen, Germany, February, 1999. P.1-6.
  21. Tufano Peter. Who Manages Risk? // An Empirical Examination of Risk Management Practices in the Gold Mining Industry: The Journal of Finance. 1996. Vol.51. N 4. P.1097-1137.

Similar articles

Plateaus on hardness curves of annealed hypoeutectoid steels at ~0.5 % C as a consequence of the presence оf ~Fe42C interim phase
2016 K. Yu. Shaznazarov, E. I. Pryakhin
А analysis and classification of resource saving technologies for reproduction of mineral resources оf titanium industry
2016 S. V. Fedoseev, Dzhada Sanneris, M. A. Tochilo
Processing of low-quality bauxite feedstock by thermochemistry-Bayer method
2016 O. A. Dubovikov, E. E. Yaskelyainen
Development and manufacturing cycle for potassium nitrate and phosphate producing by conversion method
2016 A. I. Alekseev, B. A. Dmitrievskii
Forecasting safe conditions for developing coal bed suites under aquifers on the basis of geomechanics of technogenic water conducting fractures
2016 V. N. Gusev
«Proceedings Of The Mining Institute»: history and modernization (to 110-th anniversary of first publication)
2016 I. G. Rebeshchenkova