Building of underground construction protected enclosing wall and method of displacement forecast of the soil
About authors
- 1 — National Mineral Resources University (Mining University)
- 2 — Jet Technology and Construction ltd
Abstract
The volumetric model taking and performed mathematical modeling the process of construction of the pit under the enclosing wall of secant piles. The results of mathematical modeling on the horizontal displacements of the pit wall. Set out conditions for the construction of the pit and the main technological solutions.
Similar articles
Application of laser scanning in the analysis of geometrical parameters object surface
2012 Yu. N. Kornilov, V. V. Kulesh
On cosmic rotation-pulsatory cycles of the earth and the natural-technogeneous status of objects in underground space under conditions of geodynamic instability and solar depression in 1982-2065
2012 B. G. Tarasov, E. K. Melnikov, L. V. Bugaenko
Building of construction pit and investigation of displacement wall of the secant pile
2012 S. V. Stepanenko
Estimation of condition tubbing lining escalator tunnel of metro station «Admiralty» by results of lazerno-scanning survey
2012 V. K. Nosov