The method of potash salt interchamber pillars stability control
About authors
- 1 — Ph.D., Dr.Sci. professor Mining institute, Ural branch the Russian Academy of Sciences
- 2 — Ph.D., Dr.Sci. professor Mining institute, Ural branch the Russian Academy of Sciences
- 3 — Ph.D., Dr.Sci. professor Mining institute, Ural branch the Russian Academy of Sciences
Abstract
The research of potash salt rock deforming and damaging features has made it possible to develop the method of load bearing element state examination by chamber-and-pillar system. This method consists in instrumental control of pillars by geophysical and in situ methods with following prognosis of their residual life by mathematical simulation methods.
Область исследования:
(Archived) Innovation in designing of mining plants
Funding:
None
Similar articles
Classification and methods of the accounting of investment risks of oil and gas projects
2013 O. A. Marinina
Determination of a minimum permissible thickness of interstrata in undermining of a coal seam
2013 S. G. Baranov
Shelf oil and gas projects influence on the regional economic development (on the example of «Sakhalin-1» and «Sakhalin-2» projects)
2013 A. E. Cherepovitcyn, N. V. Smirnova