Experience of inter-chamber pillar mining after consolidation of the primary chambers' backfill

Authors:
Yu. L. Minaev
A. V. Karpunin
A. G. Vasiliev
Date submitted:
1968-07-28
Date accepted:
1968-09-07
Date published:
1969-05-05

Abstract

In 1966 at the Kaula-Kotselvaara mine of the Pechanganickel Combine, experimental work was carried out on the development of an inter-chamber pillar located between the walls of the cement-reinforced backfill. Pilot works were carried out in a 6-8 m thick section of the ore body with a dip angle of 26-30°. The intervening rocks - phyllites - are partially broken by transverse fractures. In general, the ore and rock are stable. Ore strength coefficient is 8-12, rock strength coefficient is 10-12. Volume weight of the ore is 3.2 t/m3 and of the embedding material is 2.8 t/m3.

Область исследования:
(Archived) Without section
Go to volume 58

Similar articles

Physical and mechanical properties of solidifying fill in artificial pillars
1969 T. N. Smirnova
Depth of ore deposits development by open-cutting systems
1969 A. B. Makeenkov
Investigation of the stressed state of pillars under the chamber-pillar system of development at the Mayak mine
1969 V. D. Paliy, Yu. D. Orlov, V. P. Ushenin
Investigation of the influence of complex hypsometry of the ore body on the value of ore loss and dilution
1969 A. I. Shablygin, V. G. Eliseev
Computer-aided selection of optimal parameters of blocks in caving development
1969 A. A. Kavtaskin
Causes of losses of broken ore at Apatitovy mine
1969 Yu. N. Nikolaev, V. V. Shchipachev