Provision of stability of a hydraulic dump for overburden storage at Lebedinsky and Yuzhno-Lebedinsky open-pit mines of KMA

Authors:
Yu. A. Sobolevsky
N. N. Baranov
V. A. Meshkov
V. M. Pavlenko
Date submitted:
1975-08-04
Date accepted:
1975-10-20
Date published:
1976-02-01

Abstract

Lebedinsky and Yuzhno-Lebedinsky open pits of KMAruda combine are part of Lebedinsky mine. When developing these quarries, along with dry mining mechanisms, hydromechanization means are also used (in Yuzhno-Lebedinsky up to 100%, and in Lebedinsky about 10% of the total overburden). ...

Область исследования:
(Archived) Without section
Go to volume 70

Similar articles

Conditions of mineral excavation under water bodies
1976 A. S. Mironov
Mechanism of landslides in quarries
1976 A. M. Demin
Use of search and information system of engineering-geological conditions of solid mineral deposits for estimation of stability of quarry sides
1976 T. N. Ganicheva
Assessment of engineering-geological phenomena and processes in the mining zone at coal and ore deposits in connection with the tasks of environmental protection
1976 G. G. Skvortsov, V. V. Fromm, B. M. Gamalay
Experience of drawing up predictive engineering-geological maps in selecting the most promising lithological horizons for designing field mine workings in them
1976 A. A. Sidorov, V. M. Komlev, A. I. Leleko
Peculiarities of geogolic structure of coal deposits with thick deposits, determining engineering-geological conditions of their development
1976 V. V. Kiryukov