Analysis of 4PP-2M roadheader operation at Lenmetrostroy mine № 516

Authors:
A. A. Khalilov
Date submitted:
1992-09-25
Date accepted:
1992-11-29
Date published:
1993-12-28

Abstract

The technology of construction of single-wall stations of the St. Petersburg Metro provides for the development of the station core, which contains the bulk of the rock excavated during the construction of the station, after the construction of the upper vault. Until recently, this work was carried out mainly with the help of jackhammers.

Область исследования:
(Archived) Without section
Go to volume 138

Similar articles

Press for production of double-layer fuel coal briquettes
1993 Yu. D. Tarasov, V. V. Denegin, G. V. Sokolova, Yu. S. Fedorov, Yu. N. Marusov, N. K. Ulashchik
К вопросу о производительности щековой дробилки
1993 V. V. Denegin
Determination of bulk cargo motion parameters on curved surfaces with constant radius of curvature
1993 Yu. D. Tarasov
Automated calculation of optimal cutting modes during machining
1993 Yu. P. Boytsov
Calculation of connections with guaranteed interference fit for a given probability of failure-free operation
1993 E. S. Kuznetsov
Justification of design schemes of devices for mounting and dismantling works of mechanized complexes in mines of Pechora basin
1993 Yu. I. Rogov, D. A. Jungmeister