Rationale for the development of the working area of the quarry with a variable direction of deepening at maximum speed

Authors:
I. A. Ishkulova
About authors
  • Postgraduate student G.V. Plekhanov Saint Petersburg State Mining Institute
Date submitted:
2003-06-25
Date accepted:
2003-07-08
Date published:
2004-01-01

Abstract

Determination of productive capacity of open-pit mines is the main problem in designing field development by the open-cut mining method. Direction of mining operations in open-pits and characteristics of working area development in horizontal direction greatly influence result consistency in establishing productive capacity basing on mining and engineering parameters, especially when economic and mathematical methods are used.

Go to volume 159

Similar articles

Study of mixing processes in apparatuses with stirrers
2004 A. A. Markelov
Methodological issues of improving the licensing of state subsoil use in the Russian Federation
2004 L. I. Iseeva, A. V. Zelenov
Improvement of nepheline speck leaching technology based on the use of combined coagulants-flocculants of the carboaluminate-alklar type
2004 S. A. Vinogradov
Improvement of personal protective equipment for miners in the North
2004 S. P. Poltorykhin
Environmental business and the prospects for its development in Russia
2004 V. V. Kosovtsev
Justification of investments in quarry construction to replenish the raw material base of OAO Karelsky Okatysh
2004 A. S. Semenov