Reconstruction of vertical shaft of Uzelginsky mine
Authors:
About authors
- Shakhty Institute of South Russian State Technical University (Novocherkassk Polytechnic Institute)
Abstract
The paper studies details of the draft plan for skip shaft reconstruction at the Uzelginsky Ore Mine. Methods of loading chamber construction at the –340 m horizon and improvement of the shaft lining at the construction level are given a detailed description of.
References
- СНиП II-94-80. Подземные горные выработки / Госстрой СССР. М.: Стройиздат, 1982. 31 с.
- Булычев Н.С. Механика подземных сооружений: Учеб. для вузов. М.: Недра, 1994. 382 с.