Reconstruction of vertical shaft of Uzelginsky mine
Authors:
About authors
- Shakhty Institute of South Russian State Technical University (Novocherkassk Polytechnic Institute)
Abstract
The paper studies details of the draft plan for skip shaft reconstruction at the Uzelginsky Ore Mine. Methods of loading chamber construction at the –340 m horizon and improvement of the shaft lining at the construction level are given a detailed description of.
References
- СНиП II-94-80. Подземные горные выработки / Госстрой СССР. М.: Стройиздат, 1982. 31 с.
- Булычев Н.С. Механика подземных сооружений: Учеб. для вузов. М.: Недра, 1994. 382 с.
Similar articles
Establishment of regularities of action of single charge explosion at modeling on equivalent materials
2009 P. N. Shulgin
Investigation of possibility of enrichment of chromite ores of Sakseyskoye deposit
2009 K. A. Stepanova
Improvement of quality of manufacture of petrochemical devices and gas-oil pipelines by application of vibration treatment during welding
2009 O. F. Khafizova
Organization of mining works at preparation of new horizons at watered open pits
2009 I. I. Dudanov, V. S. Avraamov, D. N. Ligotsky, G. A. Kholodnyakov