Experience in providing the stability of tunnel face and roof during its drivage in proterozoic clays

Authors:
V. A. Maslak
About authors
  • Deputy Head of Board on Capital Construction The Saint-Petersburg Metro
Date submitted:
2008-10-29
Date accepted:
2008-12-11
Date published:
2009-04-01

Abstract

Methodology for assessment of state of advance support of face with fiberglass anchors and the working¢s roof – with tube anchors, is given. The results of in-situ experimental observations for efforts in anchors, displacements of excavation and growth of load on the advance supports in its roof are shown.

Keywords:
face ground anchor clay mine working stability stress deformation monitoring
Go to volume 183

References

  1. Маковский Л.В. Под защитой экрана из труб // Метрострой. 1980. № 4. С.23-24.

Similar articles

Analytical continuation of geophysical fields by continued fractions method
2009 K. M. Ermokhin
Composition of retrospective geological systems and significance of structural-tectonic factor in paleogeographic reconstructions
2009 V. P. Matveev
Nickel-containing iron oxides in the Buruktal deposit, South Urals
2009 S. O. Ryzkova, I. V. Talovina, V. G. Lazarenkov, N. I. Vorontsova, V. L. Ugolkov
The application of areal technology and 3d data interpretation tem sounding when constructing the volume geoelectrical model of compound medium
2009 G. M. Trigubovich, M. G. Persova, E. V. Krupnov, Y. G. Soloveichik
Principles of development of geological engineering and geological criteria for safe burial of low radioactive wastes in lower cambrian blue clays in the Leningrad region
2009 R. E. Dashko
Thermobaric granite crystallization conditions of the severniy massif (the Chukotka) in accordance with the feldspars study data
2009 V. I. Alekseev