Calculation methodology of physical parameters of the artificial pillar barrier

Authors:
M. N. Adreev
About authors
  • post-graduate student Saint Petersburg State Mining Institute (Technisal University)
Date submitted:
2010-07-21
Date accepted:
2010-09-08
Date published:
2011-03-21

Abstract

The article is devoted to the calculation methodology of physical parameters of the artificial barrier pillar needed when developing underquarry deposits of kimberlitic pipes in difficult hydrogeological conditions.

Область исследования:
(Archived) Development of solid mineral deposits
Keywords:
Kimberlitic tubes underquarry reserves water-bearing level compound of backfill material
Go to volume 189

References

  1. Alborov Z.B. Development of foreign deposits beneath the ponds and rivers. Moscow: Nedra, 1965.
  2. Borisov A.A. Rock mechanics and arrays. Moscow: Nedra, 1980.
  3. Kazikaev D.M. Joint development of ore deposits of the open pit and underground. Moscow: Nedra, 1967.
  4. Kaplunov D.R. Design principles of combined technologies during the development of major mineral deposits //
  5. Mining magazine. №10. 2003.
  6. Kaplunov D.R. Development of design theory, the integrated development of mineral resources in the development
  7. of the development of ore deposits // Mining magazine. 2005.
  8. Kartashov Y.M. Strength and deformability of rocks / Y.M.Kartashov, B.V.Matveev, G.V.Mikheev, A.B.Fadeev. Moscow: Nedra, 1980.
  9. Klishin V.I. Optimization of the depth of the transition from open to underground method of mining of kimberlite deposits / V.I.Klishin., A.A.Ordin, A.S.Zelberg.// Mining magazine. 2003. № 4.

Similar articles

Prospects of hydrometallurgical processing of oxidized copper ores and sulfide copper concentrate, as part of new technology оf complex processing deposit «Erdenetiin Ovoo»
2011 M. Purevdash
Usage of simulation modeling for planning and interpretation experimental-filtrational works when prospecting solid mineral product deposit
2011 S. N. Kotlov, K. E. Volodchenko
Implementation of green building standards for major territory development projects: SC «Olympstroy» experience
2011 A. O. Kharchenko, I. B. Sergeev
The control algorithm reagent conditions of flotation copper-nickel ores on the basis of оptimizing the ionic parameters
2011 A. M. Kurchukov
Definition areas of possible migration gas fromthe reservoir by cross-hole seismic tomography method
2011 N. A. Poznyakova
Parameters of high viscosity oils transportation in the form of emulsion research in order to its optimization
2011 V. I. Aleksandrov, A. P. Khrabrov