Performed mathematical modeling the process of construction of the pit under the enclosing wall of secant piles. The results of mathematical modeling on the horizontal displacements of the pit wall.
Область исследования:
(Archived) Geotechnology for development of solid mining fields
References
- Ulitsky V.M. Geotechnical support for urban development / V.M.Ulitsky, A.G.Shashkin, K.G.Shashkin. Saint Petersburg, 2010.
Similar articles
Evaluation of the stability of slopes with using native and foreign software
2012 A. M. Mochalov, S. A. Ishutin, A. A. Pavlovich, R. Yu. Sapachev
Безопасные параметры сдвижения земной поверхности при строительстве метрополитена в Санкт-Петербурге
2012 V. P. Khutskii
Analysis of load formation on lining of tunnel constructed in soil with nonlinear behavior
2012 A. G. Protosenya, V. I. Semenov, I. K. Suprun