Experience of industrial operation of CPC in 6 kV distribution networks of potash mines

Authors:
O. V. Ivanov
B. P. Konovalov
M. M. Malyushitsky
V. D. Ryzhkov
Date submitted:
1978-08-23
Date accepted:
1978-10-09
Date published:
1979-02-01

Abstract

The low quality of voltage in the centers of supply of loads of mining sites during normal operation of the distribution network required regime measures to improve it ...

Область исследования:
(Archived) Without section
Go to volume 84

Similar articles

Influence of inductance of thyristor arrester power circuit on short-circuit CPC modes
1979 S. A. Maksimov
Subordinate vector control of induction motor by rotor slip parameter
1979 V. A. Dartau
Laboratory installation for reactive power regulation
1979 N. V. Nefedova
Higher harmonics in CPC with nonlinear inductive shunt element
1979 V. G. Bauman, V. M. Kvyatkovsky, S. A. Maksimov
Control units of thyristor frequency converter in vector control system
1979 V. V. Alekseev, V. A. Dartau, Yu. P. Pavlov, V. V. Rudakov
Asynchronous machine equations for synthesis of frequency control systems
1979 I. M. Stolyarov, T. O. Rosso