Analysis of AMK unit operation at Lenmetrostroy mines

Authors:
A. A. Khalilov
Date submitted:
1990-09-03
Date accepted:
1990-11-03
Date published:
1991-04-11

Abstract

When conducting the stations of the Leningrad Metro, the tunnels are conducted first, then the calotte slot (the upper part of the station vault with a height of 3.5 m), and the main part of the station is developed with the help of excavators of the "Gidravlik" type and boom tunneling machines.

Область исследования:
(Archived) Without section
Funding:

None

Go to volume 126

Similar articles

Development of researches on application of high-pressure water jet
1991 Cheng Da Jun
О влиянии функции распределения осреднений скорости на гидравлические характеристики потока
1991 Yu. N. Gulyaev
Method of selecting the rational mode of operation of combine harvester actuators
1991 A. M. Meshkov
About application of L.Euler's equation to pumps
1991 S. S. Smorodin
On the influence of the averaged velocity distribution function on the hydraulic characteristics of the flow
1991 Yu. N. Gulyaev
Integral characteristics of sulfur-water mixture during flow in fracture fracture
1991 E. V. Sergeev, A. S. Maksimov