Analysis of AMK unit operation at Lenmetrostroy mines
Authors:
Abstract
When conducting the stations of the Leningrad Metro, the tunnels are conducted first, then the calotte slot (the upper part of the station vault with a height of 3.5 m), and the main part of the station is developed with the help of excavators of the "Gidravlik" type and boom tunneling machines.
Область исследования:
(Archived) Without section
Funding:
None
Similar articles
Resistance of a layer of deposits on a wall at destruction by a water jet
1991 K. G. Asatur, I. I. Doroshenko, V. V. Shilov
Research of thermal load of 33.00-51 tires in conditions of Kostomuksha mining and processing plant
1991 S. V. Medvedev
Frictional auto oscillations of dual mass braking devices
1991 M. M. Vetyukov, R. F. Nagaev, M. Yu. Platovskikh