Submit an Article
Become a reviewer
Vol 167 Iss. 1
Pages:
117-120
Download volume:
RUS
Article

Justification of resource-saving technological schemes of potash strata mining in areas with limited dimensions

Authors:
D. V. Urazov
About authors
  • Postgraduate student G.V. Plekhanov Saint Petersburg Mining Institute
Date submitted:
2005-06-20
Date accepted:
2005-07-24
Date published:
2006-01-01

Abstract

The paper analyzes the methods of mining operations at coal mines and potash mines of Starobinsky deposit. Special attention is paid to the problem of rational extraction of potash ore without leaving large width pillars at the mines of RUE PA Belaruskali, especially relevant at the Krasnoslobodsk mine under construction. The hypothesis of the combined method of underground mining of the 4th sylvinite layer of the Third potash horizon, which consists in mining of the pillar with limited dimensions with turning of the mechanized complex by 180° on the border of the excavation area, is put forward. The known technological schemes with face turning were analyzed and their disadvantages were determined. A new technological scheme of excavation of the 4th layer with extinguishing of the previously left pillar (for protection of preparatory workings after turning) is proposed. The necessary parameters for its application (width of the zone of operational cracks propagation to the edge part of the massif) are calculated, the approximate economic effect from the introduction of the new technological scheme is given.

Область исследования:
(Archived) Mining. Ecology
Go to volume 167

Similar articles

Improvement of technology of construction of the middle tunnel of the metro station "Zvenigorodskaya"
2006 E. P. Reznikov
Symbolism of the cross in archaic and Christian cultures
2006 R. V. Korchenkov, I. V. Trofimova
The subtleties of persuasion
2006 K. A. Burtsev
Choice of rational technology of development of V. Grib diamondiferous pipe
2006 M. A. Vorona
Ethics of catastrophes
2006 Yu. D. Larina
Investigation of the efficiency of the cutting slot to reduce seismic impact during tunnel construction
2006 E. Yu. Vinogradova