Justification of resource-saving technological schemes of potash strata mining in areas with limited dimensions

Authors:
D. V. Urazov
About authors
  • Postgraduate student G.V. Plekhanov Saint Petersburg Mining Institute
Date submitted:
2005-06-20
Date accepted:
2005-07-24
Date published:
2006-03-30

Abstract

The paper analyzes the methods of mining operations at coal mines and potash mines of Starobinsky deposit. Special attention is paid to the problem of rational extraction of potash ore without leaving large width pillars at the mines of RUE PA Belaruskali, especially relevant at the Krasnoslobodsk mine under construction. The hypothesis of the combined method of underground mining of the 4th sylvinite layer of the Third potash horizon, which consists in mining of the pillar with limited dimensions with turning of the mechanized complex by 180° on the border of the excavation area, is put forward. The known technological schemes with face turning were analyzed and their disadvantages were determined. A new technological scheme of excavation of the 4th layer with extinguishing of the previously left pillar (for protection of preparatory workings after turning) is proposed. The necessary parameters for its application (width of the zone of operational cracks propagation to the edge part of the massif) are calculated, the approximate economic effect from the introduction of the new technological scheme is given.

Область исследования:
(Archived) Mining. Ecology
Funding:

None

Go to volume 167

Similar articles

Goals, tasks and content of environmental monitoring
2006 K. S. Shanina
Relay protection and automation of substations of oilfield sites
2006 P. A. Rogov
About one algorithm of calculation of stressed state of salt reservoirs roof taking into account optimal choice of technological schemes parameters
2006 A. P. Gospodarikov, L. A. Bespalov, M. A. Zatsepin
Possibility of application of satellite radio-navigation systems in modern construction
2006 V. G. Tselovalnikov
Investigation of the efficiency of the cutting slot to reduce seismic impact during tunnel construction
2006 E. Yu. Vinogradova
Segregation of fine-grained material during gravity concentration
2006 A. M. Vasilev