Project financing structures for the russian natural resources sector

Authors:
Thomas Schumann
About authors
  • Bergakademie Freiberg
Date submitted:
2006-08-21
Date accepted:
2006-10-11
Date published:
2007-02-01

Abstract

The study examines how the lack of investment in the natural resource sector can be overcome through the application of project finance structures, which have not yet been used in Russia. The main characteristics of project finance are reviewed, its opportunities compared to traditional corporate finance are emphasized, the most common obstacles hindering the implementation of project finance schemes are considered, and the necessary steps to improve the situation are outlined.

Go to volume 170

References

  1. Bema Gold Corporation (2000): IFC Signs Mandate Letter for Julietta Project Financing, http://www.bema.com/ 337/57/news.htm [access: April 4, 2006].
  2. Claudy, P. (2002): Projektfinanzierung in Emerging Markets – eine institutionenökonomische Analyse, Sternenfels (Wissenschaft & Praxis).
  3. EBRD (1997): Sakhalin II (Phase 1) Oil Project – Project Summary Document, http://www.ebrd.com/projects/psd/ psd1997/3321.htm [access: April 4, 2006].
  4. EBRD (2001a): Natural Resources – April 2001, London (EBRD).
  5. EBRD (2001b): Transition Report 2001 – Energy in Transition, London (EBRD).
  6. EBRD (2002): SeverTEK – Project Summary Document, http://ebrd.org/projects/psd/psd2002/19677.htm [access: April 4, 2006].
  7. EBRD (2004): Middle-Timan Bauxit Mining & Processing Project – Project Summary Document, http://www. ebrd.com/projects/psd/psd2004/20318.htm [access: April 4, 2006].
  8. EBRD (2005a): Sakhalin II (Phase 2) Oil Project – Environmental Impact Assessment, http://www.ebrd.com/ projects/eias/russia/5897.htm [access: April 4, 2006].
  9. EBRD (2005b): Transition Report 2005 – Business in Transition, London (EBRD).
  10. EBRD (2005c): Trans Siberian Gold – Environmental Impact Assessment, http://www.ebrd.com/projects/eias/ russia/35364.htm [access: April 4, 2006].
  11. EBRD (2006a): EBRD and IFC welcome commitment to high governance and business standards by RUSAL Chairman Oleg Deripaska (press release), http://www. ebrd.com/new/pressrel/2006/2jan17.htm [access: April 4, 2006].
  12. EBRD (2006b): Syndications showcase, http://ebrd. org/oppor/syndi/showcase/index.htm [access: April 4, 2006].
  13. Linden, E. von der (2002): Finanzierung von Bergwerken und Bergbauausrüstungen, in: Glückauf, No. 138, p. 227-232.
  14. Nevitt, P. K. / Fabozzi, F. (2000): Project Financing, 7th edition, London (Euromoney).
  15. The Banker (2004): Russia’s Project Finance Challenge, Special Supplement October 2004.
  16. Trans-Siberian Gold (2006): TSG to go ahead with Asacha – work ongoing at Veduga, http://www. londonstockexchange.com/LSECWS/IFSPages/MarketNewsPopup. aspx?id=1164752&source=RNS [access: April 10, 2006].
  17. WWF (2004): Position Paper on Sakhalin II Oil & Gas Development, http://assets.panda.org/downloads/ wwfpositionpapersakhalin.pdf [access: April 4, 2006].
  18. Yescombe, E. R. (2002): Principles of Project Finance, Amsterdam et al. (Academic Press).

Similar articles

Geomechanical justification of tunnel parameters in construction of subway in Perm
2007 V. V. Musikhin
Production aspects of ductility minimum emperature dmt phenomenon in as cast CuNi25 alloy
2007 R. Nowosielski, P. Sakiewicz, M. Lutyński
Economic impact analysis of national natural gas storage
2007 Eun-Young Ahn
Alternative choice of the unemployed on the labor market
2007 V. M. Vasiltsova, V. S. Vasiltsov, I. V. Veter
Aquifer diffusivity determination from aquifer responses to the river stage fluctuations in a Mangyeong-river floodplain
2007 Kyoochul Ha, Dong-Chan Koh, Byoung-Woo Yum, Kang-Kun Lee
Environmental condition of natural waters in the territory of the City of Tomsk
2007 E. Yu. Pasechnik