Model of calculation of material balance of firing process on clinker for Portland cement production in rotary kiln

Authors:
Yu. V. Sharikov1
P. V. Ivanov2
About authors
  • 1 — G.V. Plekhanov Saint Petersburg Mining Institute
  • 2 — G.V. Plekhanov Saint Petersburg Mining Institute
Date submitted:
2007-10-27
Date accepted:
2007-12-26
Date published:
2008-10-23

Abstract

The essence of process of roasting charge on clinker was considered. The model of a rotating furnace was constructed in software package ReactOp. Dependences of the basic components processed charge on length of the furnace of sintering and the general change of the basic mass streams were found.

Область исследования:
(Archived) Mathematical modeling of technological processes in metallurgy
Go to volume 177

Similar articles

Character of constant component of phase voltage of ore-heat furnaces for phosphorus and calcium carbide production
2008 A. A. Pedro, V. V. Vasiliev
Products of Gemcom Software International Inc. - GEMS, Whittle, Surpac
2008 O. V. Stagurova
Methodical maintenance of use of results of the automated monitoring of self-propelled equipment and dump trucks
2008 A. A. Kuleshov
Modern approach to building automated systems of dispatch and management of mines and mines
2008 A. I. Kotlyarskiy
Training-system of hardware-software synthesis of automated control systems on the example of continuous operation unit
2008 E. D. Kadyrov, E. A. Alsufiev
Onboard control system of excavator
2008 G. A. Popov