Assessment of stress-strain state of temporary support during constructhion of station tunnels of the metro
Authors:
About authors
- Deputy Head of Board on Capital Construction The Saint-Petersburg Metro
Abstract
In-situ testing technique of temporary support is given. The values of stress and normal force in arch and sides of steel support are shown. Determination of vertical load magnitude is done. It was determined that vertical load on support decreases by 1,54 times, if lag of support installation from the face is16 m.
Область исследования:
(Archived) Drilling
References
- Lebedev M.O. Mining-ecological monitoring by the example of the large loop tunnel SKGD / M.O.Lebedev, V.V.Basykin // The etro and Tunnels. 2006. No.6, pp.24-26.
Similar articles
MODEM 3D new software for the interpretation of IP-affected 3D tem data
2009 M. I. Ivanov, V. A. Kateshov, I. A. Kremer, M. I. Epov
Electrical fields structure characteristics in tardanskii gold mineralization zone (the Republic of Tyva)
2009 A. N. Orekhov
Composition of retrospective geological systems and significance of structural-tectonic factor in paleogeographic reconstructions
2009 V. P. Matveev