Modelling stressedly-deformed condition of the soil massif including elements of the multipurpose facility with multystoried underground part
About authors
- 1 — Ph.D. associate professor National Mineral Resources University (Mining University)
- 2 — Ph.D. associate professor National Mineral Resources University (Mining University)
Abstract
In work the option of the multipurpose underground complex being part of the multystoried high-rise building is considered. The complex settles down in underground part of the building and carries out a base role, replacing with itself the usual plates-but-pile base. Predesigns by a method of final elements taking into account staging of construction of an underground complex and the land high-rise building are executed. Sizes and a picture of distribution of vertical displacements are received as a result of calculations.
Область исследования:
(Archived) Mining geomechanics
Keywords:
multifunctional underground facility
foundation
finite element method
settling
displacement
Funding:
None
References
- MDS 50-1. Design and device of the bases, bases and underground parts of multipurpose high-rise buildings and complexes / Federal State Unitary Enterprise Research Center «Stroitelstvo». Moscow, 2007.
- Guide to complex development of underground space of the large cities. Moscow, 2004.
Similar articles
Automation of architecture and urban-planning authority as the basis of strategic planning
2013 P. P. Spirin, E. B. Bejaeva, V. F. Kovyazin, E. D. Asetskaya