Measurement of the seismic blast wave during the construction of the pipeline trench near the existing pipeline

Authors:
R. A. Vosgrin1
L. V. Surovitsky2
About authors
  • 1 — student National Mineral Resources University (Mining University)
  • 2 — chief engineer «PetroGazService» LLC
Date submitted:
2013-01-06
Date accepted:
2013-03-19
Date published:
2013-12-27

Abstract

In this article describes how to calculate the safety charge mass during mass explosion at a pipeline trench construction which parallel to the existing underground pipeline. A method of calculating the maximum allowable velocity seismic blast wave in the mass explosions, for monitor the production of blasting. Presented the dependences of speed seismic blast waves on the parameters of drilling and blasting.

Область исследования:
(Archived) Topical issues in mining of ore and nonmetallic minerals
Keywords:
seismic safety blasting blasting parameters the seismic waves velocity
Go to volume 206

References

  1. Artyomov V.А. Research seismic safety conditions of production drilling and blasting operations near the existing pipeline // V.A. Artyomov, Yu.I. Vinogradov, S.V. Gustov // Explosion science. N 103/60. 2010.
  2. Medvedev S.V. Engineering seismology. Мoscow, 1962.
  3. Medvedev S.V. Seismic mining explosions. Мoscow, 1964.
  4. Recommendation P 442-81 on the production technology of blasting in frozen soil and rock in the construction of pipelines parallel to existing underground steel pipelines. VNIIST. Moscow, 1982.
  5. Sadovskiy M.A. Experimental research of the mechanical action of the explosion shock wave. Proceedings of Seismological Institute of the USSR Academy of Sciences. Moscow-Leningrad, 1945. N 116.

Similar articles

Diagnostics of the mirror-symmetrical plasma by probes of various geometry
2013 A. S. Mustafaev, A. Y. Grabovskiy
Financing of sea regional exploration: a comparative analysis of russian and canadian experiance
2013 S. V. Lysak
Evaluation of radiation environment in underground construction of Saint Petersburg subway
2013 S. G. Gendler, A. A. Yakovenko
Hydrocarbon exploration costs accounting (international practices)
2013 D. A. Yakupova, T. A. Tarabarinova
Development wells in complicated conditions
2013 K. S. Kupavykh
Choice and substantiation of dragline’s entry way at untransport working of overbaden bench in the Afanasevsky deposit
2013 M. A. Marinin, D. A. Vedrova