Quarry capacity of ore relation from bench height
About authors
- 1 — Ph.D., Dr.Sci. professor National Mineral Resources University (Mining University)
- 2 — post-graduate student National Mineral Resources University (Mining University)
Abstract
The work evaluated the impact of the bench height on the development of mining operations and quarry capacity of ore. The analysis of the height of the step depends on the area of the ore deposit within the quarry field, as well as the dependence of the length of the scope of work on the angle of the ore body.
Область исследования:
(Archived) Geotechnology for development of solid mining fields
Funding:
None
References
- Arsentyev A.I. Determination of productivity andborders of pits. Мoscow: Nedra, 1970. 283 p.
- Arsentyev A.I. Holodnyakov G.A. Design of miningoperations in the open mining. Мoscow: Nedra, 1994. 336 р.
- Troubetzkoy K.N., Krasnyansky G.L., Hronin V.V.Design quarry: 2 vols. Мoscow: Publ. house of the Academy of Mining Sciences, 2001. Vol.2. 519 p.
Similar articles
Experience of implementing electromagnetic shielding on OJSC «Mordovcement»
2014 P. S. Sedov, S. V. Kovshov, Z. N. Cherkai
Method of normal load prediction on vertical shaft lining based on nonlinear behaviour of rock mass
2014 A. G. Protosenya, Nguen Ny Bai
Forecast stress state of mass when extraction coal reserves under open pit mine in the underground mining Nui Beo (Vietnam)
2014 Nguen Van Kuang