Quarry capacity of ore relation from bench height
About authors
- 1 — National Mineral Resources University (Mining University)
- 2 — National Mineral Resources University (Mining University)
Abstract
The work evaluated the impact of the bench height on the development of mining operations and quarry capacity of ore. The analysis of the height of the step depends on the area of the ore deposit within the quarry field, as well as the dependence of the length of the scope of work on the angle of the ore body.
References
- Арсентьев А.И. Определение производительности и границ карьеров. М.: Недра, 1970. 283 с.
- Арсентьев А.И. Проектирование горных работ при открытой разработке месторождений / А.И.Арсентьев, Г.А.Холодняков. М.: Недра, 1994. 336 с.
- Трубецкой К.Н. Проектирование карьеров: В 2 т. / К.Н.Трубецкой, Г.Л.Краснянский, В.В.Хронин. М.: Изд-во Академии горных наук, 2001. Т.2. 519 с.
Similar articles
Mining units quantity determination to achieve the established open cast output and averaging ore requirements
2014 S. I. Fomin, V. A. Shevelev, M. A. Marinin
Influence of disjunctive dislocations on parameters of secure zones on flat-lying adjacent coal seams
2014 V. P. Zubov, E. R. Kovalskii, A. V. Nikiforov
Primary forecast of density-related nonstationarity of cross-section upper part
2014 I. B. Movchan, V. Yu. Asyanina