Submit an Article
Become a reviewer
Geomechanics

The field observation for the processes of settling of the ore ceiling caused by mining works at Yakovlevsky deposit

Authors:
A. G. Protosenya1
D. N. Petrov2
K. G. Sinyakin3
G. A. Martem'yanova4
  • 1 — Saint Petersburg State Mining Institute (Technical University)
  • 2 — Saint Petersburg State Mining Institute (Technical University)
  • 3 — Saint Petersburg State Mining Institute (Technical University)
  • 4 — «Metal-groupp» Co.Ltd., «Yakovlevskiy pit»
Date submitted:
2016-12-05
Date published:
2011-02-01

Abstract

The methodic of the field observation for the processes of deep benchmark displacements and configuration of the local observing station is offered. The analysis of the results of the field observations for the displacements of the ore pillar is accomplished, the isolines of settling and the isolines of the average speed of settling of the ore massif is offered.

Go to volume 190

Similar articles

Aspects of coal strata mining at the mine of the elegest deposit (the republic of Tyva)
2011 Yu. V. Gromov, D. N. Demekhin
Geodinamical variability as a cause of natural disasters and technogenic catastrophes
2011 L. K. Gorshkov, Z. B. Dekusar
Dynamic radiation control methods and instruments application peculiarities at underground points for nuclear materials storage placement, radioactive waste storages and underground nuclear thermo power plants
2011 V. G. Kondrat'ev