Determination of the front mining length for backfill mining method of complex structure carbon deposits by railway transport

Authors:
V. V. Ivanov
  • Saint Petersburg State Mining Institute (Technical University)
Date submitted:
2016-12-05
Date published:
2011-02-01

Abstract

The work describes basic features of open pit development of complex structure carbon deposits. The rational length of excavator block for different models of dragline for backfill mining method was determined. The work also gives the dependence for determining the production front length for development of complex structure carbon deposits with the use of railway service for transportation of the extracted mineral.

Go to volume 190

Similar articles

Qiuck-acting technique for the determination of rheological properties of rocks
2011 M. D. Il'inov, Yu. M. Kartashov
Providing of safe conditions for mining оf shaftbottom protective pillars in deep ore mines at Talnakh
2011 V. A. Zvezdkin, V. N. Karenin, A. G. Anokhin
Determination of maximum roof spans in the intensive mining of flat-lying coal seams at the Kuzbass basin
2011 S. G. Baranov, D. S. Vlasenko, M. A. Loginov