Topical issues in mining of ore and nonmetallic minerals

The designing of the constructions of the pillar underground station with applying of the low-settle building technology

Authors:
A. G. Protosenya1
P. A. Demenkov2
M. A. Karasev3
N. A. Belyakov4
K. P. Bezrodnyi5
V. A. Maslak6
  • 1 — Saint Petersburg State Mining University
  • 2 — Saint Petersburg State Mining University
  • 3 — Saint Petersburg State Mining University
  • 4 — Saint Petersburg State Mining University
  • 5 — JSC «Lenmetrogiprotrans»
  • 6 — JSC «Lenmetrogiprotrans»
Date submitted:
2016-11-23
Date published:
2012-01-01

Abstract

The intelligent technology of designing of the constructions of pillar  underground  station is adduced. Station is building with applying of low-settle technology, which takes into consideration main stages of the building process. The scheme of interaction of the system «support lining-soil massif» was accepted as basic scheme of calculations. The calculations of the stress-strain condition of constructions was performed with applying of finite-elements method.

Go to volume 195

Similar articles

Probabilistic approach to the assessment of energy transmissions of mining machines
2012 I. E. Zvonarev, A. S. Fokin, S. L. Ivanov
Incentive resource conservation measures for underground gas storage facilities
2012 G. S. Elizarova
Estimation of atmospheric air pollution аt construction and operation of traffic tunnel
2012 S. G. Gendler, V. A. Rogalev